WMBA 6620 Week 2 Bakery Line Project Charter Example

Practices in Project Management Walden University Free custom sample in 24 to 48h

This WMBA 6620 Week 2 bakery line project charter example authorizes a second sandwich bread line at a composite Wisconsin wholesale bakery, reading like a form rather than an essay. Purpose names the business problem, Line 1 at 96 percent of capacity and about $9 million of declined orders, and a measurable result: 4,500 loaves an hour at 85 percent equipment effectiveness by March 31, 2028. Walden WMBA 6620 asks for scope with exclusions visible, eight dated milestones and a budget with its basis, here $7.4 million including $600,000 of contingency. MBA students see stakeholders named with Zwikael and Meredith's project roles, Flyvbjerg on early estimates, high-level risks led by a 34-week oven lead time and the project manager's spending authority.

CourseWMBA 6620 Practices in Project Management
WeekWeek 2
Paper typeProject charter
LengthAbout 670 words, 5 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramMaster of Business Administration (MBA)
UpdatedOctober 2026

Free sample paper for WMBA 6620 Week 2

1

Project Charter: Line 2 at Harvest Lane Bakery, a Second Sandwich Bread Line Producing 4,500 Loaves an Hour at 85 Percent Equipment Effectiveness by March 31, 2028, for $7.4 Million

Student Name

Walden University

WMBA 6620: Practices in Project Management

Instructor Name

Month Day, Year

What this page is doingThe title states the deliverable, the measurable result, the date and the budget, the four facts a charter exists to fix.
2

Project Charter: Line 2 at Harvest Lane Bakery, a Second Sandwich Bread Line Producing 4,500 Loaves an Hour at 85 Percent Equipment Effectiveness by March 31, 2028, for $7.4 Million

Project Title and Authorization

Project: Line 2 installation and startup. Organization: Harvest Lane Bakery, a composite wholesale bakery in Green Bay, Wisconsin, that supplies sandwich bread and buns to three regional grocery chains. Sponsor: Vice President of Operations. Project manager: Plant Engineering Manager. Charter date: October 12, 2026.

This charter authorizes the project manager to plan the project, commit the approved budget within the limits below and assign plant staff to project work with their supervisors' agreement.

What this page is doingA charter reads like a form, so each heading carries facts rather than discussion.
3

Purpose

Line 1 runs about 22 hours a day, six days a week, at roughly 96 percent of its practical capacity. In the past twelve months the bakery declined about $9 million of private-label bread orders it could not produce. The project will add a second automated sandwich bread line in the unused north bay of the existing plant. Success means Line 2 producing 4,500 loaves an hour at an overall equipment effectiveness of at least 85 percent, averaged over the four weeks ending March 31, 2028, with no food safety nonconformance in its first customer audit.

Scope Boundary

In scope: renovation of the north bay; a mixer, divider, proofer, tunnel oven, cooling spiral and slicer-bagger; gas and electrical service upgrades; food safety validation of the new line; hiring and training of 24 line operators and two maintenance technicians.

Out of scope: new product development, since Line 2 will run existing recipes; changes to Line 1; changes to the distribution fleet or warehouse; changes to the bakery's enterprise resource planning system beyond adding the new line's codes.

What this page is doingExclusions are written into the charter itself, so the first scope arguments are settled before they start.
4

Milestones

Table 1

Summary Milestones

MilestoneTarget date |
Charter approvedOctober 30, 2026 |
Equipment purchase orders placedDecember 15, 2026 |
North bay renovation completeJune 30, 2027 |
Oven and major equipment deliveredAugust 31, 2027 |
Installation and utility connections completeNovember 30, 2027 |
Commissioning and food safety validation completeJanuary 31, 2028 |
First commercial productionFebruary 14, 2028 |
Performance target metMarch 31, 2028 |

Dates are targets for planning; the baseline schedule will be set in the scope and schedule documents.

Budget

Approved budget: $7.4 million, including a contingency of $600,000 held by the sponsor. The estimate is a preliminary order-of-magnitude figure based on two vendor budgetary quotes and the bakery's 2019 Line 1 refurbishment, expected to fall within 10 percent either way once quotes are firm. Large projects routinely exceed budgets set this early (Flyvbjerg, 2014), so the charter asks for a firm estimate at the end of the scope phase, before the oven order is placed.

Key Stakeholders

The plant manager, who will run Line 2 after handover; the food safety and quality manager, who must approve validation; the maintenance supervisor; the bakery workers' union local, whose agreement governs new shift patterns; the three grocery customers' quality auditors; the oven vendor; and the gas utility, which must upgrade the service line. Zwikael and Meredith (2018) distinguish the project owner, funder and manager, among other roles; here the Vice President of Operations is both owner and funder, and the plant manager is the principal user.

High-Level Risks

Oven lead time, currently quoted at 34 weeks, is the largest schedule risk. The gas utility's service upgrade has no committed date. Hiring 24 operators in a tight local labor market may delay startup. Each will be assessed in the risk register.

Authority and Approval

The project manager may approve spending up to $50,000 per item within the budget and may reassign tasks within the team. Changes to scope, milestones after June 30, 2027, or total cost require the sponsor's approval through change control. In the PMBOK Guide's terms, a charter is what officially brings a project into being and lets its manager commit company resources to it (Project Management Institute, 2021); this one takes effect once the sponsor and the plant manager sign it.

Signatures: Vice President of Operations; Plant Manager; Plant Engineering Manager.

References

Flyvbjerg, B. (2014). What you should know about megaprojects and why: An overview. Project Management Journal, 45(2), 6-19. https://doi.org/10.1002/pmj.21409

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.).

Zwikael, O., & Meredith, J. R. (2018). Who's who in the project zoo? The ten core project roles. International Journal of Operations & Production Management, 38(2), 474-492. https://doi.org/10.1108/IJOPM-05-2017-0274

What the WMBA 6620 Week 2 instructions ask for

The charter assignment asks students to write the document that formally authorizes a project. Instructors expect one to three pages under fixed headings, reading more like a form than an essay. Purpose should name the business problem and a measurable result with a date. Scope should appear as a boundary statement with the first exclusions visible. A milestone list of five to eight dated entries, a budget with its basis and accuracy, key stakeholders and high-level risks usually follow. The charter closes with the project manager's authority and the signatures that make it effective. Strong charters avoid vague goals and state numbers wherever the case allows. The budget figure should say how it was estimated and how accurate it is likely to be, since early estimates are rarely final. Naming who may approve changes keeps later decisions orderly.

How this WMBA 6620 Week 2 example is built

The charter names the project, sponsor, project manager and date and states the authority it grants. Purpose explains Line 1's utilization and the declined orders, then defines success in output, equipment effectiveness and audit terms. Scope lists six in-scope items and four exclusions. A table gives eight milestones with dates. The budget section states $7.4 million with contingency and its basis, citing Flyvbjerg on early estimates and asking for a firm estimate later. Stakeholders are named with Zwikael and Meredith's role distinctions. Three high-level risks are listed. The close sets spending authority, refers changes to change control, cites the PMBOK Guide on charters and lists signatures. Margin comments flag the form-like structure and the exclusions.

WMBA 6620 Week 2 rubric: what earns full marks

Graders reward a charter with a measurable, dated purpose rather than a general aim. A scope boundary that names exclusions earns credit because it prevents later disputes. Dated milestones and a budget with its basis and accuracy show realism. Identifying stakeholders and their roles, and naming the main risks, demonstrates planning awareness. Clear statements of the project manager's authority and the approval needed for changes show governance. A charter a sponsor could sign as written, with no paragraph that needs a follow-up meeting to interpret, sits at the top of the range. Charters that name the largest risk and its effect on a milestone show the most foresight.

Common WMBA 6620 Week 2 mistakes, and how to avoid them

Start by writing the business problem in two sentences and the result you will measure, with a date. List what is in scope and, just as carefully, what is not. Choose five to eight milestones that a sponsor would recognize. Give a budget with its basis and how accurate it is. Students often lose marks by stating goals such as improving efficiency, by omitting exclusions or by leaving authority unclear. Another frequent gap is a budget with no explanation. Keep each section short and factual. If you would like a custom sample charter for a project you are planning, send us its purpose and budget.

Get a WMBA 6620 Week 2 example written to your instructions

The charter prompt and its rubric start it, along with any required template the section distributes and the project wherever the assignment names one. A complete charter with milestones, budget, roles and numbered assumptions arrives in 24 to 48 hours, the first one free. Client and vendor names never appear in a draft.

More WMBA 6620 papers and MBA samples

WMBA 6620 Week 2 questions, answered

Where can I find a free WMBA 6620 Week 2 sample paper?

Scroll down: the charter for adding a second line at a wholesale bakery is printed in full, with comments in the margin.

What does the project deliver?

A second sandwich bread line producing 4,500 loaves an hour at 85 percent equipment effectiveness.

What is the budget?

$7.4 million, including $600,000 of contingency held by the sponsor.

What is excluded?

New recipes, Line 1 changes, fleet or warehouse changes and most system changes.

What is the largest risk?

The oven's 34-week lead time.