This WMBA 6620 Week 10 earned value status report example fits a bakery line project's week 30 status onto a page, opening with three lines: overall condition amber, the main issue a damaged floor slab putting renovation 13 weeks behind and $95,000 over, and two requests. A metrics table reports planned value, earned value and actual cost, an SPI that has slipped to 0.90, a CPI sitting at 0.95 and an estimate at completion near $6.63 million. Walden WMBA 6620 asks for indices read with judgment, and the report explains, citing Anbari, why a low schedule index off the critical path leaves the end date unchanged. MBA students see accomplishments tied to work packages and issues and risks with responses.

CourseWMBA 6620 Practices in Project Management
WeekWeek 10
Paper typeStatus report
LengthAbout 720 words, 5 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramMaster of Business Administration (MBA)
UpdatedOctober 2026

Free sample paper for WMBA 6620 Week 10

1

Line 2 Status Report, Week 30: Amber Overall, Renovation Behind and Over on the Floor Slab but the Oven-Driven Critical Path on Time, With SPI 0.90, CPI 0.95 and Two Requests to the Sponsor

Student Name

Walden University

WMBA 6620: Practices in Project Management

Instructor Name

Month Day, Year

What this page is doingThe title gives the condition, the main issue, the two indices and the requests, the summary a sponsor reads first.
2

Line 2 Status Report, Week 30: Amber Overall, Renovation Behind and Over on the Floor Slab but the Oven-Driven Critical Path on Time, With SPI 0.90, CPI 0.95 and Two Requests to the Sponsor

Status Summary

Overall condition: amber. Main issue: unforeseen damage to the north bay floor slab has put renovation 13 weeks behind and about $95,000 over its estimate; the critical path, driven by the oven, is on schedule. Requests: approval to draw $95,000 from contingency for the slab, and the sponsor's help securing a date from the gas utility.

Reporting period: weeks 27 to 30, ending May 31, 2027. Project: Line 2 bread line expansion, Harvest Lane Bakery (composite case).

What this page is doingThe three-line summary carries the condition, the single most important issue and the request.
3

Metrics

Table 1

Earned Value at Week 30

MeasureValue |
Budget at completion, baseline version 1.1$6,298,282 |
Planned value to date$2,410,000 |
Earned value to date$2,180,000 |
Actual cost to date$2,295,000 |
Schedule varianceMinus $230,000 |
Cost varianceMinus $115,000 |
Schedule performance index0.90 |
Cost performance index0.95 |
Estimate at completion, at current cost performanceAbout $6,630,000 |

Budget at completion excludes the escalation allowance and contingency; version 1.1 includes the approved oven change.

The indices need reading together with the schedule. A schedule performance index of 0.90 means the project has earned about 90 percent of the value planned by now. Almost all of the shortfall is in renovation and utility work, which had 21 and 22 weeks of float at baseline. The critical path, procurement and oven manufacture, is on plan: the vendor's May progress report shows the oven frame and conveyor belt complete, matching its schedule. Anbari (2003) noted that schedule variance measured in dollars can mislead when the shortfall sits off the critical path, and that is the case here. The forecast end date is unchanged at January 3, 2028.

The cost performance index of 0.95 is driven by the floor slab. If cost performance stayed at 0.95 for the rest of the project, the estimate at completion would be about $6.63 million, about $330,000 over the baseline and within the $600,000 contingency plus the remaining management reserve. That forecast is pessimistic, because most remaining cost is fixed-price equipment.

Accomplishments Since Last Report

1. Floor slab, package 1.2.2: cracked sections removed and new slab poured over the east half of the bay; the west half is scheduled for weeks 31 and 32.

2. Electrical service and panels, package 1.3.2: passed city inspection on May 18, later than baseline but well within its float.

3. Oven manufacture: the vendor's May progress report shows work on schedule for the August factory acceptance test.

4. Wall panels and ceiling, package 1.2.3: materials ordered for delivery in week 31 so installation can follow the slab without a gap.

5. Workforce, package 1.7.1: recruitment plan for 24 operators approved by human resources and the union; advertising begins June 14.

What this page is doingAccomplishments are tied to work packages, so progress can be checked against the breakdown rather than taken on trust.
4

Issues and Risks

Issue: floor slab. Demolition exposed cracked slab sections over about 2,600 square feet, requiring removal and repour before coating. Cost: about $95,000. Schedule: renovation now finishes in week 33 instead of week 20, still 8 weeks before installation needs the bay, so float falls from 21 weeks to 8. This was the second-largest item in the contingency, estimated at $160,000.

Risk: gas utility. The utility has not yet confirmed a construction date for the service upgrade. The schedule allows the upgrade to finish as late as week 50, so there is time, but the risk rises each month without a date. Response: sponsor contact with the utility's commercial account executive.

Risk: oven factory acceptance test. If the oven fails its temperature uniformity test in August, a retest could delay shipment. Response: the plant engineer will attend the vendor's internal pretest in July.

Requests

1. Approve drawing $95,000 from contingency for the floor slab repair, leaving $505,000.

2. Call the gas utility's account executive to secure a construction date before the June 30 report.

The PMBOK Guide (Project Management Institute, 2021) describes status reporting as a way to support decisions, not only to record progress, and these two requests are the decisions this report needs. Fleming and Koppelman (2010) recommend tracking the indices monthly so that early trends can be acted on, and the next report will show whether cost performance recovers once slab work ends.

References

Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403

Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.).

Reading the WMBA 6620 Week 10 instructions

The status report assignment asks students to report a project's condition to its sponsor in a page or two. Instructors expect a status summary of three lines: overall condition, the single most important issue and what is being requested. A metrics block follows with schedule and cost variance stated numerically, usually as earned value indices with the underlying figures, plus a forecast at completion. Accomplishments since the last report should be tied to deliverables rather than activity. Issues and risks appear with their effects and responses. The report closes with specific requests for decisions. Indices should be interpreted against the critical path and remaining float, because a low schedule index does not always mean a late finish. The forecast at completion should state the method used.

How the WMBA 6620 Week 10 example is put together

The report opens with condition, issue and requests, then the reporting period. A metrics table lists budget at completion, planned value, earned value, actual cost, variances, indices and the estimate at completion. A paragraph explains why the schedule index reflects work with float rather than the critical path, citing Anbari, and why the cost forecast is pessimistic. Five accomplishments are tied to work packages. Issues and risks cover the floor slab, the gas utility and the oven factory test, each with a response. Two requests ask for contingency and the sponsor's help with the utility, citing the PMBOK Guide and Fleming and Koppelman. Margin comments flag the summary and the work package links. The whole report fits on one page plus the metrics table.

WMBA 6620 Week 10 rubric: what earns full marks

The strongest reports open by stating the project's condition, the one issue behind it and the request to the sponsor. Accurate earned value calculations, shown with their underlying figures, carry significant weight. Interpreting the indices with reference to the critical path shows judgment rather than mechanical reporting. Accomplishments tied to deliverables and issues with responses demonstrate control. Specific requests make the report actionable. A sponsor should be able to act on the report after reading only its first block, which is the standard most graders hold it to. Reports that explain whether a variance threatens the end date, rather than only reporting its size, show the strongest judgment. Plain language that a sponsor can act on quickly is expected throughout.

Common WMBA 6620 Week 10 mistakes, and how to avoid them

Write the condition, the main issue and your request in three lines before anything else. Compute planned value, earned value and actual cost, then the variances and indices. Ask whether any shortfall is on the critical path before saying the project is late. List what was finished, tied to work packages. Students often lose marks by reporting activity rather than results, by presenting indices without interpretation or by burying the request. Forecasts pulled from thin air, with no stated method, cost marks too. State how you calculated it. If you need a custom sample status report for your project, send us its earned value figures.

Get a WMBA 6620 Week 10 example written to your instructions

The reporting prompt, the rubric, and the baseline figures this report measures against are what it takes. A one-page report with variance, forecast, issues and a dated ask comes back in 24 to 48 hours, the first one free. Where a section supplies a template, the draft fills that template rather than ours.

More WMBA 6620 papers and MBA samples

WMBA 6620 Week 10 questions, answered

Where can I find a free WMBA 6620 Week 10 sample paper?

The earned value status report for week 30 of a bakery line project is published in full here.

What is the overall condition?

Amber, because of floor slab damage, with the critical path on time.

What are the indices?

Schedule efficiency at 0.90 and cost efficiency at 0.95, by the earned value indexes.

Why is the end date unchanged?

The schedule shortfall is in work with float, while the oven-driven critical path is on plan.

What does the report request?

Approval to use $95,000 of contingency and the sponsor's help with the gas utility.