Line 2 Status Report, Week 30: Amber Overall, Renovation Behind and Over on the Floor Slab but the Oven-Driven Critical Path on Time, With SPI 0.90, CPI 0.95 and Two Requests to the Sponsor
Student Name
Walden University
WMBA 6620: Practices in Project Management
Instructor Name
Month Day, Year
Line 2 Status Report, Week 30: Amber Overall, Renovation Behind and Over on the Floor Slab but the Oven-Driven Critical Path on Time, With SPI 0.90, CPI 0.95 and Two Requests to the Sponsor
Status Summary
Overall condition: amber. Main issue: unforeseen damage to the north bay floor slab has put renovation 13 weeks behind and about $95,000 over its estimate; the critical path, driven by the oven, is on schedule. Requests: approval to draw $95,000 from contingency for the slab, and the sponsor's help securing a date from the gas utility.
Reporting period: weeks 27 to 30, ending May 31, 2027. Project: Line 2 bread line expansion, Harvest Lane Bakery (composite case).
Metrics
Table 1
Earned Value at Week 30
| Measure | Value | |
|---|---|
| Budget at completion, baseline version 1.1 | $6,298,282 | |
| Planned value to date | $2,410,000 | |
| Earned value to date | $2,180,000 | |
| Actual cost to date | $2,295,000 | |
| Schedule variance | Minus $230,000 | |
| Cost variance | Minus $115,000 | |
| Schedule performance index | 0.90 | |
| Cost performance index | 0.95 | |
| Estimate at completion, at current cost performance | About $6,630,000 | |
Budget at completion excludes the escalation allowance and contingency; version 1.1 includes the approved oven change.
The indices need reading together with the schedule. A schedule performance index of 0.90 means the project has earned about 90 percent of the value planned by now. Almost all of the shortfall is in renovation and utility work, which had 21 and 22 weeks of float at baseline. The critical path, procurement and oven manufacture, is on plan: the vendor's May progress report shows the oven frame and conveyor belt complete, matching its schedule. Anbari (2003) noted that schedule variance measured in dollars can mislead when the shortfall sits off the critical path, and that is the case here. The forecast end date is unchanged at January 3, 2028.
The cost performance index of 0.95 is driven by the floor slab. If cost performance stayed at 0.95 for the rest of the project, the estimate at completion would be about $6.63 million, about $330,000 over the baseline and within the $600,000 contingency plus the remaining management reserve. That forecast is pessimistic, because most remaining cost is fixed-price equipment.
Accomplishments Since Last Report
1. Floor slab, package 1.2.2: cracked sections removed and new slab poured over the east half of the bay; the west half is scheduled for weeks 31 and 32.
2. Electrical service and panels, package 1.3.2: passed city inspection on May 18, later than baseline but well within its float.
3. Oven manufacture: the vendor's May progress report shows work on schedule for the August factory acceptance test.
4. Wall panels and ceiling, package 1.2.3: materials ordered for delivery in week 31 so installation can follow the slab without a gap.
5. Workforce, package 1.7.1: recruitment plan for 24 operators approved by human resources and the union; advertising begins June 14.
Issues and Risks
Issue: floor slab. Demolition exposed cracked slab sections over about 2,600 square feet, requiring removal and repour before coating. Cost: about $95,000. Schedule: renovation now finishes in week 33 instead of week 20, still 8 weeks before installation needs the bay, so float falls from 21 weeks to 8. This was the second-largest item in the contingency, estimated at $160,000.
Risk: gas utility. The utility has not yet confirmed a construction date for the service upgrade. The schedule allows the upgrade to finish as late as week 50, so there is time, but the risk rises each month without a date. Response: sponsor contact with the utility's commercial account executive.
Risk: oven factory acceptance test. If the oven fails its temperature uniformity test in August, a retest could delay shipment. Response: the plant engineer will attend the vendor's internal pretest in July.
Requests
1. Approve drawing $95,000 from contingency for the floor slab repair, leaving $505,000.
2. Call the gas utility's account executive to secure a construction date before the June 30 report.
The PMBOK Guide (Project Management Institute, 2021) describes status reporting as a way to support decisions, not only to record progress, and these two requests are the decisions this report needs. Fleming and Koppelman (2010) recommend tracking the indices monthly so that early trends can be acted on, and the next report will show whether cost performance recovers once slab work ends.
References
Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403
Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.).
Reading the WMBA 6620 Week 10 instructions
The status report assignment asks students to report a project's condition to its sponsor in a page or two. Instructors expect a status summary of three lines: overall condition, the single most important issue and what is being requested. A metrics block follows with schedule and cost variance stated numerically, usually as earned value indices with the underlying figures, plus a forecast at completion. Accomplishments since the last report should be tied to deliverables rather than activity. Issues and risks appear with their effects and responses. The report closes with specific requests for decisions. Indices should be interpreted against the critical path and remaining float, because a low schedule index does not always mean a late finish. The forecast at completion should state the method used.
How the WMBA 6620 Week 10 example is put together
The report opens with condition, issue and requests, then the reporting period. A metrics table lists budget at completion, planned value, earned value, actual cost, variances, indices and the estimate at completion. A paragraph explains why the schedule index reflects work with float rather than the critical path, citing Anbari, and why the cost forecast is pessimistic. Five accomplishments are tied to work packages. Issues and risks cover the floor slab, the gas utility and the oven factory test, each with a response. Two requests ask for contingency and the sponsor's help with the utility, citing the PMBOK Guide and Fleming and Koppelman. Margin comments flag the summary and the work package links. The whole report fits on one page plus the metrics table.
WMBA 6620 Week 10 rubric: what earns full marks
The strongest reports open by stating the project's condition, the one issue behind it and the request to the sponsor. Accurate earned value calculations, shown with their underlying figures, carry significant weight. Interpreting the indices with reference to the critical path shows judgment rather than mechanical reporting. Accomplishments tied to deliverables and issues with responses demonstrate control. Specific requests make the report actionable. A sponsor should be able to act on the report after reading only its first block, which is the standard most graders hold it to. Reports that explain whether a variance threatens the end date, rather than only reporting its size, show the strongest judgment. Plain language that a sponsor can act on quickly is expected throughout.
Common WMBA 6620 Week 10 mistakes, and how to avoid them
Write the condition, the main issue and your request in three lines before anything else. Compute planned value, earned value and actual cost, then the variances and indices. Ask whether any shortfall is on the critical path before saying the project is late. List what was finished, tied to work packages. Students often lose marks by reporting activity rather than results, by presenting indices without interpretation or by burying the request. Forecasts pulled from thin air, with no stated method, cost marks too. State how you calculated it. If you need a custom sample status report for your project, send us its earned value figures.
Get a WMBA 6620 Week 10 example written to your instructions
The reporting prompt, the rubric, and the baseline figures this report measures against are what it takes. A one-page report with variance, forecast, issues and a dated ask comes back in 24 to 48 hours, the first one free. Where a section supplies a template, the draft fills that template rather than ours.
More WMBA 6620 papers and MBA samples
- WMBA 6620 Week 1: Missed Project Target Post
- WMBA 6620 Week 2: Bakery Line Project Charter
- WMBA 6620 Week 3: Project Scope Statement
- WMBA 6620 Week 4: Work Breakdown Structure
- WMBA 6620 Week 5: Critical Path Schedule Build
- WMBA 6620 Week 6: Bottom-Up Project Cost Estimate
- WMBA 6620 Week 7: Plan Reconciliation Peer Replies
- WMBA 6620 Week 8: Project Quality Plan
- WMBA 6620 Week 9: Change Control Procedure
- WMBA 6620 Week 11: Project Closeout Report
- WMBA 6623 Week 10: Risk Escalation Protocol
- WMBA 6615 Week 10: Culture Investment Brief
- WMBA 6627 Week 10: Executive Stakeholder Briefing Note
- WMBA 6608 Week 1: Third-Party Payment Post
WMBA 6620 Week 10 questions, answered
Where can I find a free WMBA 6620 Week 10 sample paper?
The earned value status report for week 30 of a bakery line project is published in full here.
What is the overall condition?
Amber, because of floor slab damage, with the critical path on time.
What are the indices?
Schedule efficiency at 0.90 and cost efficiency at 0.95, by the earned value indexes.
Why is the end date unchanged?
The schedule shortfall is in work with float, while the oven-driven critical path is on plan.
What does the report request?
Approval to use $95,000 of contingency and the sponsor's help with the gas utility.