Closeout Report for Line 2: Handed Over Two Weeks Late and $6.71 Million Against a $7.4 Million Approval, Performance Target Met at 4,520 Loaves an Hour, With Acceptance, Administrative Closure and Five Lessons
Student Name
Walden University
WMBA 6620: Practices in Project Management
Instructor Name
Month Day, Year
Closeout Report for Line 2: Handed Over Two Weeks Late and $6.71 Million Against a $7.4 Million Approval, Performance Target Met at 4,520 Loaves an Hour, With Acceptance, Administrative Closure and Five Lessons
Performance Against Baseline
Harvest Lane Bakery's Line 2 project, set at a composite Green Bay plant, put a second sandwich bread line into the north bay and brought it to rate. This report closes the project as of April 14, 2028.
Scope. All seven deliverables were completed. No scope was added beyond the one approved change, the heat recovery oven, and no scope was removed.
Schedule. Handover slipped two weeks, from January 3 to January 17, 2028. The cause was the oven's factory acceptance test in August 2027, which found temperature variation at the belt edges above the vendor's specification. The vendor adjusted burner settings and retested, and shipment slipped one week. A second week was lost when bake validation in December required a third run after one loaf on the left edge read below the set point. Because the charter's first production date of February 14 sat six weeks after the planned handover, the slip did not affect customers.
Cost. Actual cost exceeded the version 1.1 baseline by about $414,000, or 6.6 percent. Three items account for most of it: the floor slab repair, about $95,000; a higher gas utility contribution, $132,000 instead of $85,000; and extended installer time and project management for the two-week slip, about $118,000. The rest came from smaller overruns in commissioning materials and training overtime. The escalation allowance and contingency together covered the overrun, leaving management reserve untouched. The final cost of $6.71 million stands about $690,000 below the $7.4 million approval.
Table 1
Final Performance Against Baseline
| Dimension | Baseline | Actual | Variance | |
|---|---|---|---|
| Scope | Seven deliverables in the scope statement | Seven delivered and accepted; one with conditions, since closed | None | |
| Handover date | January 3, 2028 | January 17, 2028 | Two weeks late | |
| First commercial production | February 14, 2028 | February 14, 2028 | None | |
| Cost, excluding contingency and reserve | $6,298,282, baseline version 1.1 | $6,712,400 | $414,118 over baseline; within the $7.4 million approval | |
| Performance target, four weeks ending March 31, 2028 | 4,500 loaves an hour at 85% equipment effectiveness | 4,520 loaves an hour at 86.1% | Met | |
Cost figures include the approved heat recovery oven change; firms and figures are composite.
Acceptance
The sponsor, the Vice President of Operations, signed final acceptance on February 2, 2028, against the acceptance criteria in the scope statement. The plant manager signed for the handover package on the same date, with one condition: two sanitation procedures, for the cooling spiral and the slicer-bagger, were still in draft. Both were approved by the food safety manager on February 4, and the condition was closed. The first customer audit of Line 2, by the largest grocery chain's quality team on March 9, found one minor nonconformance, a missing calibration record for a probe thermometer, corrected the same day. The performance target was confirmed by the plant's production reports for the four weeks ending March 31.
Administrative Closure
Contracts. The general contractor, plumbing and electrical contracts were closed after final inspections and lien waivers. Retainage of 10 percent on each equipment purchase order was released after installation qualification, except for the oven's heat recovery unit, where $14,000 remains held until the vendor's two-year gas savings guarantee is reconciled in February 2030.
Purchase orders and accounts. All 41 project purchase orders are closed. The project cost account was closed on April 10 and its balance transferred to the fixed asset register, with the equipment placed in service on February 14, 2028.
Records. The schedule, cost records, change log, nonconformance log, quality records and validation reports are archived in the engineering document system. The risk register has been closed with the outcome of each risk recorded.
Team. The project manager returned to the plant engineering role. Contract installers were released in January.
Lessons Learned
Lessons logged at closeout often never reach the next project's practice (Williams, 2008), so every lesson below is tied to a specific change and an owner.
First, survey existing slabs before estimating. Core samples of the north bay floor, costing perhaps $4,000, would have found the cracked sections before the estimate was set. Change: core sampling is now a required step in the bakery's capital project checklist for any work on existing floors.
Second, engage the gas utility before charter approval. The utility's contribution rose by more than half once its design was done, and its date remained uncertain for months. Change: future projects will request a utility feasibility review during the business case.
Third, attend vendor pretests. The plant engineer's presence at the oven vendor's internal pretest in July 2027 shortened the response when the formal test failed. Change: vendor pretests are now standard for equipment over $500,000.
Fourth, delay hiring deliberately. Starting recruitment about seven months after ordering, rather than at project start, brought operators on board close to installation and avoided months of idle wages. Change: the lag will be used as a template.
Fifth, treat contingency as a register, not a percentage. Building contingency from identified risks meant two of the three largest overruns had been anticipated and funded. Overruns are the norm rather than the exception on major projects (Flyvbjerg, 2014), and this project's 6.6 percent overrun against baseline, covered by planned contingency, is a modest result by that standard.
The lessons have been entered in the bakery's capital projects folder, and the plant engineering manager will review them with the team planning the next line refurbishment, starting with the slab survey and the utility review.
Transition and Benefits
Line 2 is now part of the plant's operations, and its performance is reported in the plant's weekly production meeting. The project's business case depended on capturing declined private-label orders; by the end of March, the sales team had signed two private-label contracts worth about $6.8 million a year. The PMBOK Guide (Project Management Institute, 2021) treats benefits realization as continuing after a project closes, and the plant controller will report Line 2's contribution against the business case at six and twelve months.
References
Flyvbjerg, B. (2014). What you should know about megaprojects and why: An overview. Project Management Journal, 45(2), 6-19. https://doi.org/10.1002/pmj.21409
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.).
Williams, T. (2008). How do organizations learn lessons from projects, and do they? IEEE Transactions on Engineering Management, 55(2), 248-266. https://doi.org/10.1109/TEM.2007.912920
The Walden WMBA 6620 Week 11 instructions
The closeout report documents how a project ended and what the organization learned. Instructors expect five parts across twelve hundred to eighteen hundred words. Performance against baseline opens the report, with final numbers for scope, schedule and cost and a paragraph explaining each variance. Acceptance follows, naming who signed, when and against which criteria, with any conditions. Administrative closure covers contracts, purchase orders, accounts, records and the release of the team. Lessons learned should be specific and tied to changes in practice. Handover to plant operations, and the way the line's promised benefits will be measured after closeout, form the last part. Final cost should be compared with both the baseline and the approved budget, and the use of contingency and reserve explained. Customer or regulatory audits after handover belong in the acceptance section.
How the WMBA 6620 Week 11 example is put together
The report opens with a table comparing baseline and actual scope, handover date, first production, cost and performance. Paragraphs explain the two-week slip, traced to the oven acceptance test and a third validation run, and the cost overrun, traced to the floor slab, the gas contribution and the slip. An acceptance section names the sponsor's and plant manager's signatures, a closed condition and the first customer audit. Administrative closure covers contracts, retainage, purchase orders, accounts, records and the team. Five lessons, citing Williams and Flyvbjerg, each name a change in practice. A transition section describes new contracts and benefits reporting, referring to the PMBOK Guide for closing processes. Side notes mark the final numbers and the administrative closure steps. Final figures are reconciled to the change log and the approved budget.
Reading the WMBA 6620 Week 11 rubric
Graders reward a closeout report that opens with accurate final numbers against baseline and explains each variance. Acceptance details, including conditions and how they were closed, show completeness. Administrative closure covering contracts, accounts and records demonstrates discipline. Lessons learned that lead to specific changes in practice carry significant weight. Describing the transition and how benefits will be measured shows awareness that value continues after the project. Lessons tied to a named date and decision, rather than offered as general advice, give the closeout its value for the next line project. Reports that name who will track benefits and when show that the project's purpose outlasts its closure.
WMBA 6620 Week 11 help: mistakes that cost marks
Gather the final figures for scope, schedule and cost and set them beside the baseline. For each variance, write what caused it. Record who accepted the project, when and with what conditions. List every contract, account and record that must be closed. Then write lessons that name a change the organization will make. Students often lose marks by restating variances without causes, by writing lessons as general advice or by forgetting administrative closure. Another frequent gap is ending without saying how benefits will be tracked. If you would like a custom sample closeout report for your project, send us its final figures.
Get a WMBA 6620 Week 11 example written to your instructions
Send the closeout prompt, its rubric, and whatever the earlier weeks produced, since the final numbers have to agree with them. A report with variance explanations, recorded acceptance, the administrative checklist and structured findings arrives in 24 to 48 hours, the first one free. Employer records stay where they are.
More WMBA 6620 papers and MBA samples
- WMBA 6620 Week 1: Missed Project Target Post
- WMBA 6620 Week 2: Bakery Line Project Charter
- WMBA 6620 Week 3: Project Scope Statement
- WMBA 6620 Week 4: Work Breakdown Structure
- WMBA 6620 Week 5: Critical Path Schedule Build
- WMBA 6620 Week 6: Bottom-Up Project Cost Estimate
- WMBA 6620 Week 7: Plan Reconciliation Peer Replies
- WMBA 6620 Week 8: Project Quality Plan
- WMBA 6620 Week 9: Change Control Procedure
- WMBA 6620 Week 10: Earned Value Status Report
- WMBA 6623 Week 11: Quarterly Enterprise Risk Report
- WMBA 6615 Week 11: Organizational Culture Change Plan
- WMBA 6627 Week 11: Final Stakeholder Management Report
- WMBA 6608 Week 1: Third-Party Payment Post
WMBA 6620 Week 11 questions, answered
Where can I find a free WMBA 6620 Week 11 sample paper?
The closeout report for the finished bakery line, including its final cost and schedule variances, is printed below in full.
Was the project on time?
Handover was two weeks late, but first commercial production met its February 14 date.
What did it cost?
About $6.71 million, over the $6.30 million baseline but under the $7.4 million approval.
Was the performance target met?
Yes, 4,520 loaves an hour at 86.1 percent equipment effectiveness.
What lessons were recorded?
Survey slabs before estimating, engage utilities early, attend vendor pretests, delay hiring deliberately and build contingency from risks.