Bottom-Up Cost Estimate for Line 2: $6.14 Million Across the Work Packages, a $150,000 Escalation Allowance and $600,000 of Risk-Based Contingency, Coming In About $510,000 Under the Charter Figure
Student Name
Walden University
WMBA 6620: Practices in Project Management
Instructor Name
Month Day, Year
Bottom-Up Cost Estimate for Line 2: $6.14 Million Across the Work Packages, a $150,000 Escalation Allowance and $600,000 of Risk-Based Contingency, Coming In About $510,000 Under the Charter Figure
Summary
Every work package of Line 2, the bread line expansion at the composite Harvest Lane Bakery, carries a price in this estimate. The base estimate is about $6.14 million. Adding a 3 percent escalation allowance on equipment and construction, about $150,000, and a risk-based contingency of $600,000 brings the total to about $6.89 million. That is about $510,000 below the $7.4 million the charter approved, a difference within the charter's stated accuracy of 10 percent either way.
The Estimate
Table 1
Cost Estimate by Work Package
| Work package | Quantity and rate | Source of rate | Total | |
|---|---|---|---|
| 1.1 Project management | Project manager 1,830 h at $85; purchasing manager 300 h at $70 | Bakery loaded labor rates, 2026 | $176,550 | |
| 1.2.1 Remove old racking | Maintenance 160 h at $48 | Loaded labor rate | $7,680 | |
| 1.2.2 Slab repair and epoxy floor coating | 18,000 sq ft at $14.00 | General contractor budget quote GC-114 | $252,000 | |
| 1.2.3 Wall panels and ceiling | Lump sum | General contractor budget quote GC-114 | $198,000 | |
| 1.2.4 Extend floor drains | Lump sum | Plumbing contractor quote P-0417 | $46,000 | |
| 1.2.5 Inspection and walk-through | City fees $3,500; food safety manager 16 h at $62 | City fee schedule; loaded rate | $4,492 | |
| 1.3.1 Gas service upgrade | Utility construction contribution | Gas utility preliminary estimate | $85,000 | |
| 1.3.2 Electrical service and panels | Lump sum | Electrical contractor quote E-2210 | $412,000 | |
| 1.3.3 Compressed air extension | Materials $18,000; maintenance 80 h at $48 | Supplier catalog; loaded rate | $21,840 | |
| 1.3.4 Utility testing and certification | Lump sum | Electrical contractor quote E-2210 | $6,000 | |
| 1.4.1 Specifications and vendor selection | Plant engineer 240 h at $72 | Loaded labor rate | $17,280 | |
| Production equipment, purchased under 1.4.2 | Mixer $310,000; divider and proofer $640,000; tunnel oven $1,980,000; cooling spiral $520,000; slicer-bagger $385,000; conveyors and guarding $260,000 | Vendor budgetary quotes Q-2291 to Q-2296 | $4,095,000 | |
| 1.4.3 Factory acceptance test | Two staff, four days | Bakery travel policy rates | $6,400 | |
| 1.4.4 Freight and delivery | Lump sum | Freight forwarder quote F-88 | $68,000 | |
| 1.5 Installation labor | Oven installers $210,000; other installers $145,000; maintenance 600 h at $48 | Vendor quotes; loaded rate | $383,800 | |
| 1.6 Commissioning and validation | Startup engineers $72,000; trial dough and scrap $38,000; supervisor 120 h at $55; food safety manager 40 h at $62 | Vendor quote; ingredient cost; loaded rates | $119,080 | |
| 1.7 Workforce | Recruiting $26,000; training wages 26 people for 160 h at $24; trainer 160 h at $55 | Agency quote; wage scale | $134,640 | |
| 1.8 Handover | Procedures 160 h at $72; initial spare parts $95,000 | Loaded rate; vendor spare parts list | $106,520 | |
| Base estimate | Sum of 1.1 through 1.8 | Work package lines above | $6,140,282 | |
| Escalation allowance | 3% of $5,003,000 in equipment and construction | Quote validity of 90 days | $150,000 | |
| Contingency | Risk-based, held by sponsor | Risk register, see below | $600,000 | |
| Total | Base plus escalation and contingency | Lines above | $6,890,282 | |
Labor hours and rates are shown separately so either can be challenged; firms and figures are composite.
Basis of Estimate
Three methods were used, depending on the kind of cost.
Equipment and construction, about 81 percent of the base, were estimated from vendor and contractor budgetary quotes. The equipment quotes come from the shortlisted vendors and include their standard installation supervision but not the installers' labor, which appears separately. The construction quotes are budgetary, given before final drawings, and typically move by 5 to 15 percent when they become firm bids. Freight is from a forwarder's quote for the oven's oversize loads.
Internal labor was estimated bottom-up. Each work package owner estimated the hours their staff would spend, and those hours were priced at the bakery's 2026 loaded rates, which include wages, benefits and payroll taxes. Project management hours assume 30 hours a week for the project manager over 61 weeks. Training wages assume four weeks of full-time training for 26 new hires, paid at the entry wage.
Utility and permit costs came from the gas utility's preliminary estimate and the city's published fee schedule. The gas figure is the least reliable number in the estimate, because the utility will not commit to a final contribution until its design is done in spring 2027.
Several costs are excluded: Line 1 downtime, since construction is limited to Sunday shutdowns; the cost of capital during construction, which finance carries separately; and post-handover operating costs, which belong to the plant's operating budget.
Escalation and Contingency
The escalation allowance covers price increases between quote dates and order dates. Equipment and construction quotes are valid for 90 days, and most orders will be placed three to six months after quoting, so a 3 percent allowance on those categories is reasonable.
Contingency covers identified risks. It was built from the risk register rather than set as a flat percentage, and schedule uncertainty, which Herroelen and Leus (2005) identify as a central weakness of deterministic plans, drives its largest item: about $220,000 for a possible oven delivery delay, which would extend installer and project management costs; about $160,000 for unforeseen floor slab conditions found during demolition; about $120,000 for a higher gas utility contribution; and about $100,000 for slower hiring requiring overtime during commissioning. Flyvbjerg (2006) argued that estimators systematically underestimate costs because they plan from the inside view of their own project, and recommended checking estimates against the outcomes of similar past projects. The bakery's 2019 Line 1 refurbishment ran 11 percent over its estimate, close to the contingency's 9.8 percent of base.
What to Do With the Difference
The estimate's total is about $510,000 below the charter budget. I recommend that the sponsor keep the $7.4 million approval in place but treat the difference as unallocated management reserve until the oven order is placed and the construction bids are firm. Releasing it now would remove the cushion against the estimate's largest uncertainties, which are concentrated in the budgetary construction quotes and the gas contribution. The PMBOK Guide (Project Management Institute, 2021) distinguishes contingency for identified risks from management reserve for unknown ones, and the difference here fits the second category until the estimate is firmer.
References
Flyvbjerg, B. (2006). From Nobel Prize to project management: Getting risks right. Project Management Journal, 37(3), 5-15. https://doi.org/10.1177/875697280603700302
Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289-306. https://doi.org/10.1016/j.ejor.2004.04.002
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.).
Reading the WMBA 6620 Week 6 instructions
The cost estimate assignment asks students to price a project's work in a way others can check. Instructors expect a table first, with a row per work package carrying quantity, unit rate, the source of the rate and a total. Labor rows should keep hours separate from rates. Non-labor rows should cite a quote, catalog or published index. A basis of estimate section, often about four hundred words, names the method used for each group of rows and the assumptions behind rates. Contingency should appear separately with its basis, and the estimate should be compared with the approved budget. Exclusions also belong in the basis section.
How this WMBA 6620 Week 6 example is built
The paper opens with a summary comparing the total with the charter budget. A table prices eighteen rows, from project management labor to spare parts, and adds escalation and contingency. The basis of estimate explains vendor and contractor quotes for equipment and construction, bottom-up hours for internal labor and the utility and permit figures, then lists exclusions. A section explains the escalation allowance and builds contingency from four named risks, citing Herroelen and Leus on schedule uncertainty and Flyvbjerg on reference class checks, and compares it with a past project. The close recommends keeping the approval and treating the difference as management reserve, again drawing on the PMBOK Guide. The margin notes single out the one-paragraph summary and the basis section. Every rate in the table names its source so a reviewer can trace it.
Reading the WMBA 6620 Week 6 rubric
Graders reward an estimate that prices every work package with traceable rates and sources. Separating hours from rates and citing quotes for non-labor items shows rigor. A basis of estimate that names methods and assumptions for each group of costs carries significant weight. Contingency built from identified risks, rather than a flat percentage, demonstrates sophistication. Comparing the estimate with the approved budget and recommending what to do with any difference shows judgment. Totals that reconcile from work package to control account to budget, with the reserve kept on its own line, protect the marks for accuracy. Estimates that name their least reliable figure, and explain how it will be firmed up, show particular care.
WMBA 6620 Week 6 help from the desk
Price each work package separately, starting with the largest. For labor, estimate hours with the people doing the work and multiply by a loaded rate. For purchases, get quotes or catalog prices and note their dates. Explain your method for each group of costs in a short basis section. Then list the main risks and estimate what each could cost to build contingency. Students often lose marks by giving totals without sources, by mixing hours and dollars or by adding a flat contingency without explanation. Another frequent gap is ignoring the approved budget. Share your work packages and any vendor quotes, and a custom cost estimate can be modeled on them.
Get a WMBA 6620 Week 6 example written to your instructions
This one runs on the estimating prompt, its rubric, and the schedule the costs attach to. A costed table with basis, contingency method and month-by-month phasing arrives in 24 to 48 hours, the first one free. Rates shown on this page stand in for real ones and get replaced by whatever the assignment supplies.
More WMBA 6620 papers and MBA samples
- WMBA 6620 Week 1: Missed Project Target Post
- WMBA 6620 Week 2: Bakery Line Project Charter
- WMBA 6620 Week 3: Project Scope Statement
- WMBA 6620 Week 4: Work Breakdown Structure
- WMBA 6620 Week 5: Critical Path Schedule Build
- WMBA 6620 Week 7: Plan Reconciliation Peer Replies
- WMBA 6620 Week 8: Project Quality Plan
- WMBA 6620 Week 9: Change Control Procedure
- WMBA 6620 Week 10: Earned Value Status Report
- WMBA 6620 Week 11: Project Closeout Report
- WMBA 6623 Week 6: Quantitative Risk Analysis
- WMBA 6615 Week 6: Culture Analysis Peer Replies
- WMBA 6627 Week 6: Workplace Conflict Case Analysis
- WMBA 6608 Week 6: Capital Project Appraisal
WMBA 6620 Week 6 questions, answered
Where can I find a free WMBA 6620 Week 6 sample paper?
The bottom-up cost estimate for a bakery line project is reproduced in full below.
What is the base estimate?
About $6.14 million across all work packages.
How is contingency set?
At $600,000, built from four risks in the register rather than a flat percentage.
How does the total compare with the charter?
About $510,000 under the $7.4 million approval.
What should happen to the difference?
It should be held as management reserve until the oven order and construction bids are firm.