This WMBA 6620 Week 5 critical path schedule build example turns a bakery line project's work packages into 27 activities with predecessors, durations, early and late dates and float, computed from a November 2, 2026 start. Dependencies are finish-to-start, and three lags carry reasons: 31 weeks of oven manufacture, a 12-week utility queue and a deliberate 24-week delay before hiring. Walden WMBA 6620 asks for the critical path, and the paper traces it through procurement, installation, commissioning and handover to a 61-week finish, citing Kelley and Walker. MBA students see float of 21 weeks on renovation, near-critical oven assembly, a missed purchase order milestone, Herroelen and Leus on uncertainty and compression options from the PMBOK Guide.

CourseWMBA 6620 Practices in Project Management
WeekWeek 5
Paper typeProject schedule
LengthAbout 1,090 words, 6 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramMaster of Business Administration (MBA)
UpdatedOctober 2026

Free sample paper for WMBA 6620 Week 5

1

A 61-Week Schedule for Line 2: Twenty-Seven Activities Drawn From the Work Breakdown, Typed Dependencies, Three Lags With Reasons, a Critical Path Set by the Oven and Where the Float Sits

Student Name

Walden University

WMBA 6620: Practices in Project Management

Instructor Name

Month Day, Year

What this page is doingThe title gives the duration and the driver of the critical path, then names the parts of the schedule a reader must be able to check.
2

A 61-Week Schedule for Line 2: Twenty-Seven Activities Drawn From the Work Breakdown, Typed Dependencies, Three Lags With Reasons, a Critical Path Set by the Oven and Where the Float Sits

Basis of the Schedule

This network schedule sequences the work for Line 2, the bread line being added at the composite Harvest Lane plant on Green Bay's west side. Every activity below is a work package from the work breakdown structure and keeps its number. The four project management packages run throughout and are not scheduled as discrete activities. Durations are in weeks, estimated by each package's owner. Week 0 begins on Monday, November 2, 2026, after the charter is approved. All dependencies are finish-to-start unless a lag is shown, and each lag has a reason given below the table.

Kelley and Walker (1959) introduced the critical path method to find the longest chain of dependent activities, the chain that sets the project's duration, and that is the purpose of the early and late dates computed here.

What this page is doingThe schedule's source and conventions come first, so every bar can be traced back to the work breakdown.
3

Activity Table

Table 1

Line 2 Activities, Dependencies, Dates and Float, in Weeks From November 2, 2026

ActivityPredecessorsWeeksESEFLSLFFloat |
1.4.1 Specs frozen, vendors chosenNone606060 |
1.4.2 POs issued1.4.1167670 |
1.4.3 Oven FAT at vendor plant1.4.2 (lag 31 wk)1383938390 |
1.4.4 Equipment shipped and received1.4.32394139410 |
1.2.1 Racking removalNone202212321 |
1.2.4 Drain extension1.2.1325232621 |
1.2.2 Slab and floor finish1.2.48513263421 |
1.2.3 Panels and ceiling work1.2.261319344021 |
1.2.5 Inspection and sanitation walk1.2.311920404121 |
1.3.1 Larger gas service1.4.1 (lag 12 wk)101828405022 |
1.3.2 Power and panels1.4.18614425036 |
1.3.3 Air line run1.2.321921485029 |
1.3.4 Utilities tested and certified1.3.1, 1.3.2, 1.3.312829505122 |
1.5.1 Mixer, divider, proofer set1.2.5, 1.4.43414441440 |
1.5.2 Oven assembly and hookup1.2.5, 1.4.46414742481 |
1.5.3 Spiral cooler and bagger in1.5.14444844480 |
1.5.4 Conveyors and guarding1.5.2, 1.5.33485148510 |
1.6.1 IQ1.5.4, 1.3.42515351530 |
1.7.1 Hiring of crew1.4.2 (lag 24 wk)12314337496 |
1.7.2 Training1.7.14434749536 |
1.6.2 Dry runs, dough trials1.6.1, 1.7.23535653560 |
1.6.3 Bake and metal detector validation1.6.22565857591 |
1.6.4 Food safety plan revised1.6.31585959601 |
1.7.3 Operator sign-offs1.7.2, 1.6.12535558605 |
1.8.1 SOPs written1.6.24566056600 |
1.8.2 Spares and warranties1.4.434144576016 |
1.8.3 Handover signed1.6.4, 1.7.3, 1.8.1, 1.8.21606160610 |

Float is late start minus early start. Week 61 ends on January 3, 2028.

The Three Lags

The 31-week lag between placing purchase orders and the factory acceptance test is the oven vendor's manufacturing time. The vendor quoted 34 weeks from order to delivery, which this schedule splits into 31 weeks of manufacture, one week of factory testing and two weeks of freight.

The 12-week lag before the gas service upgrade is the utility's scheduling queue. The utility cannot begin design until the bakery confirms the oven's gas demand, which comes from final specifications, and it then schedules field crews about three months out.

The 24-week lag before hiring begins is deliberate. Starting recruitment in mid-June 2027 brings new operators on board in late summer, close to installation, so the bakery does not pay a full crew for months before the line exists.

What this page is doingEach lag carries its reason, because an unexplained lag usually hides an assumption.
4

The Critical Path

Procurement, installation, commissioning and handover make up the critical path: 1.4.1, 1.4.2, the manufacturing lag, 1.4.3, 1.4.4, 1.5.1, 1.5.3, 1.5.4, 1.6.1, 1.6.2, 1.8.1 and 1.8.3, a total of 61 weeks. Every week of delay on any of these moves handover. The oven assembly, 1.5.2, and validation, 1.6.3 and 1.6.4, are near-critical with one week of float.

The schedule's shape is clear: the oven's lead time dominates everything. The renovation, with 21 weeks of float, and the utilities, with 22 to 36 weeks, are far from critical, which gives the project room to absorb construction problems but not oven delays. A schedule built on single-point durations treats every estimate as certain, which Herroelen and Leus (2005) flag as its main weakness; here the 34-week oven quote is the number most likely to move.

Comparison With the Charter Milestones

The schedule meets six of the charter's eight milestones with margin; one is missed, and the last, the March 2028 performance target, falls after handover and is measured in production. Equipment arrives in mid-August against an August 31 target. Renovation finishes in March 2027 against a June target; installation finishes in late October against a November target; validation finishes in late December against a January 31, 2028 target; and handover on January 3 leaves six weeks before the February 14 first production date.

One milestone is missed: purchase orders are placed in the week ending December 21, 2026, about a week after the charter's December 15 target. Because ordering is on the critical path, this matters. The project manager will ask the sponsor to accept the revised date, or the team can shorten vendor selection by a week by running the final specification review and vendor negotiation in parallel.

Schedule Risks and Responses

The largest risk is the oven. The team will request monthly manufacturing progress reports from the vendor and negotiate a late-delivery penalty in the purchase order. If the vendor signals a delay, two responses are available: having the installers work extended shifts to shorten 1.5.1 through 1.5.4, or starting operating procedures, 1.8.1, during the trials rather than after them. The second is a fast-tracking move that would shorten the path by up to two weeks at the cost of revising procedures after trials. The PMBOK Guide (Project Management Institute, 2021) describes both crashing and fast-tracking as options for compressing a schedule, each with its own cost or risk.

References

Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289-306. https://doi.org/10.1016/j.ejor.2004.04.002

Kelley, J. E., & Walker, M. R. (1959). Critical-path planning and scheduling. In Papers presented at the December 1-3, 1959, eastern joint IRE-AIEE-ACM computer conference (pp. 160-173). https://doi.org/10.1145/1460299.1460318

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.).

WMBA 6620 Week 5 instructions, in plain terms

The schedule assignment asks students to build a project schedule from their work breakdown. Instructors expect a network diagram or bar chart with dependencies and a table listing every activity with predecessors, duration, early and late dates and float. Activities should carry the breakdown's codes so any bar traces back to its package. Dependencies should be typed, mostly finish-to-start, and any lead or lag should have a stated reason. The critical path should be identified and explained, along with near-critical activities. Strong schedules compare results with charter milestones and discuss the risks most likely to move the end date. Activity durations should come from the people who will do the work, and the schedule's start date and time units should be stated plainly. Comparing the computed finish with the sponsor's deadline is part of the task.

How the WMBA 6620 Week 5 example is put together

The paper states its source, units and start date and cites Kelley and Walker on the critical path method. A table lists 27 activities with predecessors, durations, early and late starts and finishes and float. A section explains each of the three lags. A critical path section traces the longest chain, notes near-critical activities and observes that the oven dominates, citing Herroelen and Leus on uncertain durations. A comparison with the charter finds six milestones met and the purchase order date missed by a week, with two remedies. A risk section proposes monitoring the oven vendor and two compression options, with the PMBOK Guide as its source. Notes in the margin point to the basis of estimate and the lags. All dates are counted in weeks from the charter's approval.

WMBA 6620 Week 5 rubric: what earns full marks

Graders reward a schedule whose activities trace to the work breakdown and whose dates and float are computed correctly. Typed dependencies and explained lags show discipline. Identifying the critical path and near-critical activities, and explaining what drives them, carries significant weight. Comparing the schedule with charter milestones shows integration. Discussing schedule risks and realistic compression options demonstrates judgment. Forward and backward passes that agree with each other, with float shown for every activity off the critical path, earn the arithmetic marks outright. Schedules that explain why a large float exists, and what could consume it, show the strongest judgment.

WMBA 6620 Week 5 help: mistakes that cost marks

List every work package as an activity with its code. Ask what must finish before each can start, and note any waiting time with its reason. Get durations from the crews and vendors who will actually perform each activity. Run the forward pass for early dates, the backward pass for late ones, and take the difference as float. Students often lose marks by inventing activities not in the breakdown, by leaving lags unexplained or by miscalculating float. Another frequent gap is ignoring charter milestones the schedule misses. Say which ones and what you will do. A model schedule for your own project can be built from a list of its activities, their durations and what each depends on.

Get a WMBA 6620 Week 5 example written to your instructions

Send the scheduling prompt with the rubric and the breakdown this schedule has to be built from. A network or bar chart with the activity table, critical path and float returns in 24 to 48 hours, the first one free. Naming the software a section expects matters, since output format changes what can be handed over.

More WMBA 6620 papers and MBA samples

WMBA 6620 Week 5 questions, answered

Where can I find a free WMBA 6620 Week 5 sample paper?

The critical path schedule for a bakery line project is posted in full on this page.

How long is the schedule?

Sixty-one weeks, from November 2, 2026 to January 3, 2028.

What drives the critical path?

The oven's 34-week lead time, followed by installation, commissioning and handover.

Which activities have the most float?

Renovation, with 21 weeks, and the utility work, with 22 to 36 weeks.

Which charter milestone is missed?

Placing purchase orders, about a week after the December 15 target.