MMHA 6111 Week 8 Change Implementation Workplan Example

Leadership and Organizational Change Walden University Free custom sample in 24 to 48h

This MMHA 6111 Week 8 workplan example moves an imaging consolidation through three phases, prepare, move and stabilize, and gives every task a responsible role, an accountable role, a consulted role, its weeks, its resources and a note on which patients or staff would notice if it slipped. Walden MMHA 6111 asks MHA students for a plan a department could run from Monday, and the paper's table covers tasks from building a merged booking template to relocating an MRI scanner under vendor supervision. A resource ledger totals staff hours and outside services, following the Project Management Institute's guide. The critical path, risks with contingencies and a section on involving the people who do the work, citing Oreg and colleagues, follow. The close ties milestones to Kotter's short-term wins.

CourseMMHA 6111 Leadership and Organizational Change
WeekWeek 8
Paper typeImplementation workplan paper
LengthAbout 1,000 words, 6 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramMaster of Healthcare Administration (MHA)
UpdatedOctober 2026

Free sample paper for MMHA 6111 Week 8

1

Site Cutover Workplan: Prepare, Move and Stabilize, With an Owner for Every Task

Student Name

Walden University

MMHA 6111: Leadership and Organizational Change

Instructor Name

Month Day, Year

What this page is doingPromising an owner for every task in the title answers the most common failure of implementation plans.
2

Site Cutover Workplan: Prepare, Move and Stabilize, With an Owner for Every Task

Summary

This workplan carries the imaging consolidation, Westside's closure and its MRI's move to the hospital, through three phases. Prepare runs from April 1 to June 13. Move runs from June 16 to June 30, with Westside closing to patients after its last appointments on Friday, June 20, and the MRI scanner relocated the following week. Stabilize runs through July. Every task has a role responsible for doing it and a role accountable for its completion, and the plan notes which patients or staff would notice if each task slipped. All dates, hours and costs are illustrative.

What this page is doingA half-page summary states the three phases and the date the satellite closes to patients.
3

The Workplan

Table 1 lists the main tasks. R is the role responsible for doing the work; A is the single role accountable for its completion; C is consulted.

Table 1

Cutover Workplan by Phase

Phase and taskR / A / CWeeksResourcesWho notices if it slips
Prepare: build merged booking templateScheduling supervisor and Westside front desk lead / Imaging manager / RadiologistsApril 1 to May 980 scheduler hoursPatients booked into slots that do not exist
Prepare: merge on-call rotationBoth lead technologists / Imaging manager / Union stewardApril 14 to May 2320 lead hoursTechnologists unsure who is on call
Prepare: notify referring offices and update order formsImaging medical director's office / Imaging manager / Referring officesApril 1 to May 9Mailings; 30 callsPatients sent to a closed site
Prepare: site preparation for MRIFacilities / Director of facilities / MRI vendorApril 1 to June 13Shielding and power work by contractorMRI cannot be installed on schedule
Move: rebook Westside appointments after June 20Central scheduling / Imaging manager / Westside front deskMay 26 to June 2060 scheduler hoursPatients arriving at Westside to find it closed
Move: relocate MRI scannerMRI vendor / Director of facilities / Imaging managerJune 23 to June 27Vendor crew; rigging; acceptance testingMRI capacity gap at the hospital
Move: retire Westside CT and X-rayBiomedical engineering / Director of facilitiesJune 23 to June 30DecommissioningLease penalty if site not cleared
Stabilize: daily huddle and issue logBoth lead technologists / Imaging managerJuly15 minutes dailyProblems repeat without being fixed
What this page is doingThe workplan table lists tasks by phase with responsibility, timing and resources.
4

Resource Ledger

The plan uses about 140 scheduler hours, 60 lead technologist hours and roughly 40 hours of the imaging manager's time over the prepare and move phases, beyond normal duties. Scheduler hours will be covered by temporary overtime and by Westside's two front desk staff, whose own work winds down as the site closes. Outside services include the MRI vendor's relocation crew and acceptance testing, the facilities contractor for shielding and power at the hospital site and a rigging company. These are budgeted in the consolidation's capital plan. The project management standard that informs this ledger emphasizes that a plan is credible only if its resources are identified alongside its tasks (Project Management Institute, 2021).

What this page is doingA resource ledger totals staff hours by role and lists outside services.
5

The Critical Path

Two chains of tasks determine the move date. The first is the MRI site preparation: shielding and power work must finish before the scanner can be relocated, and the scanner must be relocated before the hospital can offer the added outpatient MRI capacity. A delay of two weeks in site preparation would leave a gap in MRI capacity in July, because Westside's MRI would be offline while the hospital had no space ready. The second is the merged booking template: rebooking Westside's appointments into hospital slots cannot begin until the template exists. If the template slips past May 9, rebooking compresses into fewer weeks, and the risk of patients arriving at a closed site rises. The manager will review both chains weekly.

What this page is doingThe critical path is named, so the manager knows which slip moves the whole plan.
6

Risks and Contingencies

Vendor delay. If the MRI relocation is delayed, Westside's MRI could remain in service at Westside for up to two additional weeks under a short lease extension the landlord has agreed in principle to grant; the decision point is June 6. Rebooking failures. Some patients will not be reached. On June 23 and 24, a staff member will be posted at Westside's door with a list of rebooked appointments and transport vouchers to the hospital. Staff absence during the move. The merged on-call rotation starts June 16, two weeks before the move is complete, so coverage gaps surface early.

What this page is doingNaming risks with contingencies shows the plan was written for a real Monday.
7

Involving the People Who Do the Work

Several tasks are assigned to the people whose work will change, rather than to managers. Schedulers from both sites build the merged template; both lead technologists merge the on-call rotation, with the union steward consulted; the Westside front desk lead is consulted on rebooking, because she knows which patients need a call rather than a letter. This is deliberate. Across sixty years of studies, Oreg and colleagues found participation in the change process repeatedly tied to more favorable reactions from the people undergoing it (Oreg et al., 2011). Involvement also improves the work itself: Westside's front desk lead identified about forty patients who would need help with transport to the hospital, a list no one at the hospital could have produced. Each involved staff member is given protected time for the task, counted in the resource ledger, so that involvement does not become one more thing done between patients.

What this page is doingShowing staff involvement in the workplan connects implementation to how people respond to change.
8

How the Workplan Connects to the Rest of the Plan

The workplan responds to the gaps identified in the impact grid. Building the merged template with schedulers from both sites addresses their knowledge gap and gives them ownership. Merging the on-call rotation early addresses hospital technologists' awareness that the change is theirs too. Notifying referring offices three times addresses their awareness gap. The stabilize phase's daily huddle begins the neutral-zone work the anchoring plan will describe. Kotter's call for visible early wins, followed by building on them (Kotter, 2012), shapes the plan's milestones: the first week of shorter MRI waits at the hospital should be announced to all staff as the first visible gain of the consolidation.

What this page is doingThe close connects the workplan to the impact grid and anchoring plan, so it is not a separate to-do list.
9

References

Kotter, J. P. (2012). Leading change. Harvard Business Review Press.

Oreg, S., Vakola, M., & Armenakis, A. (2011). Change recipients' reactions to organizational change: A 60-year review of quantitative studies. Journal of Applied Behavioral Science, 47(4), 461-524. https://doi.org/10.1177/0021886310396550

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.

Reading the MMHA 6111 Week 8 instructions

Implementation workplans in a change plan usually ask how the change will be carried out. Organize tasks by phase, and for each task name the role responsible, the single role accountable and anyone consulted, with timing and resources. Note who would notice if each task slipped, which shows its importance. Total the resources in a ledger, including staff hours by role and outside services. Identify the critical path, the chain of tasks that sets the completion date, and say how it will be monitored. Name risks with specific contingencies. Show how staff whose work changes are involved in tasks, with protected time. Connect the workplan to earlier analysis, such as the impact grid, so it is not a separate to-do list.

Inside the MMHA 6111 Week 8 example

The summary states three phases and the June 20 closing to patients. Table 1 lists eight tasks with responsible, accountable and consulted roles, weeks, resources and who notices a slip. The resource ledger totals scheduler, lead and manager hours and outside services, citing the Project Management Institute. The critical path section names MRI site preparation and the merged template. The risks section covers vendor delay, rebooking failures and absences. A section on involvement cites Oreg and colleagues and describes a front desk lead identifying forty patients needing transport. The closing ties tasks to the impact grid's gaps and milestones to Kotter's short-term wins.

Reading the MMHA 6111 Week 8 rubric

Workplans are judged on whether someone could run them. A list of tasks without owners, dates or resources earns little credit. Assigning one accountable role per task earns the first share. Resources totaled in a ledger, and a note on who notices a slip, show realism. Identifying the critical path earns a large share, because it tells the manager what to watch. Risks with specific contingencies show foresight. Involving the people whose work changes, with protected time, connects implementation to how people respond to change. Linking tasks to earlier analysis shows the plan is coherent. Clear tables and citations complete the assessment.

MMHA 6111 Week 8 help: mistakes that cost marks

Implementation plans often become timelines of milestones with no one responsible and no resources counted. Begin by listing every task the change requires, then assign one person accountable for each and the people who do the work. Ask how many hours each task takes and where those hours come from. Find the chain of tasks that, if it slipped, would move the whole date, and watch it weekly. Finally, ask which tasks the affected staff should do themselves, and give them time to do them. We can write an implementation workplan with owners, resources, a critical path and contingencies for your change. A plan that names who is accountable for each task is one a department can run.

Get a MMHA 6111 Week 8 example written to your instructions

Mention any required format, a Gantt chart or a RACI table for instance, when sending the Week 8 prompt and rubric. The workplan lands inside 24-48 hours, and there is no fee on the first. Naming the change your plan follows lets every task line up with the installments already drafted.

More MMHA 6111 papers and MHA samples

MMHA 6111 Week 8 questions, answered

Where can I find a free MMHA 6111 Week 8 sample paper?

The cutover workplan and its tables can be read here without charge.

What phases does the MMHA 6111 Week 8 workplan use?

Prepare, move and stabilize, with the satellite closing to patients on June 20.

What is the critical path?

MRI site preparation and the merged booking template, which together determine the move date.

What contingencies are planned?

A short lease extension if the MRI move slips, staff at the old site's door with rebooked appointments and an early start to the merged on-call rotation.

How are staff involved?

Schedulers build the template, leads merge the on-call rotation and the front desk lead advises on rebooking, each with protected time.