BUSI 3010 Week 4 Bottleneck Analysis Example

Operations Management Walden University Free custom sample in 24 to 48h

This BUSI 3010 Week 4 bottleneck analysis example times seven stations at a composite stone fabrication shop and finds that the CNC edging machine, not the templaters everyone blames, limits output to 15.2 kitchen jobs a week. Walden BUSI 3010 wants the constraint found by cycle time rather than by complaint, so the sample sets out measured hours per job, parallel resources and weekly capacity for each station, confirms the CNC figure against actual output and explains why templating only looks slow. It then shows what happens as the constraint moves: 20 jobs if the CNC reaches its standard time, with installation next at 25. Work waiting on carts links throughput to lead time. The theory of constraints from Goldratt and Cox anchors the argument, which is pitched at undergraduates in the BS in Business Administration.

CourseBUSI 3010 Operations Management
WeekWeek 4
Paper typeBottleneck analysis
LengthAbout 1,000 words, 6 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramBS in Business Administration
UpdatedOctober 2026

Free sample paper for BUSI 3010 Week 4

1

The Constraint Is the CNC, Not the Templaters: A Bottleneck Analysis of Seven Stations at a Stone Fabrication Shop, Throughput of 15.2 Jobs a Week and What Happens When the Constraint Moves to the Installation Crews

Student Name

Walden University

BUSI 3010: Operations Management

Instructor Name

Month Day, Year

What this page is doingThe title names the constraint, the station everyone blamed instead, the throughput and the next constraint, which is the order the analysis follows.
2

The Constraint Is the CNC, Not the Templaters: A Bottleneck Analysis of Seven Stations at a Stone Fabrication Shop, Throughput of 15.2 Jobs a Week and What Happens When the Constraint Moves to the Installation Crews

The Question

Everyone at Red River Stone & Surface, the composite shop used in this course, agrees that templating is the problem. Customers wait about a week for a templater to measure their cabinets, and they say so on the phone. This analysis asks a narrower question: which station limits how many kitchen jobs the shop can finish in a week? The answer comes from measured cycle times rather than from where the complaints arrive.

What this page is doingThe analysis starts from the complaint so the evidence can be seen overturning it.
3

Method

For two weeks in July 2028, I timed every job at each of seven stations, from the start of work on the job to the moment it moved on, excluding time spent waiting in front of the station. Twenty-nine jobs were timed at every station. Where a station has more than one person or crew working in parallel, the effective cycle time is the measured time per job divided by the number of parallel resources. Each station has 50 scheduled hours a week, the same ten-hour, five-day schedule used last week.

Cycle Times and Station Capacity

Table 1

Measured Cycle Times and Weekly Capacity by Station

StationHours per job, measuredParallel resourcesEffective hours per jobJobs per week at 50 hours |
Templating1.62 templaters0.8062.5 |
Programming0.91 programmer0.9055.6 |
Bridge saw1.81 saw1.8027.8 |
CNC edging3.31 machine3.3015.2 |
Hand polishing2.22 polishers1.1045.5 |
Quality and seam prep0.71 lead0.7071.4 |
Installation6.03 crews2.0025.0 |

Times are averages for 29 jobs timed in July 2028; the shop is composite. Installation hours are crew hours including travel.

Finding the Constraint

The constraint is the station with the longest effective cycle time, because no process can finish jobs faster than its slowest step. That station is the CNC, at 3.3 hours per job. At 50 hours a week, it can finish 50 ÷ 3.3 = 15.2 jobs. Every other station can handle at least 25.

The figure checks out against the shop's records. Actual output over the first half of 2028 averaged 15.2 jobs a week, exactly the CNC's measured capacity. If another station were the constraint, output would match that station's figure instead.

The measured CNC time, 3.3 hours, is longer than the 2.5-hour standard used in last week's capacity calculation. The difference comes from three sources seen during timing: the operator slows the feed rate on dark quartz to avoid chipping, adding about 25 minutes on those jobs; first pieces are rerun when the program needs correcting; and the machine sits loaded but idle while the operator waits for the gantry crane to bring the next slab section. Those losses are why the efficiency figure was below 90 percent.

What this page is doingThe constraint is identified by the longest effective cycle time, and the claim is checked against actual output.
4

Why Templating Looks Like the Problem

Templating has the shortest effective cycle time of any production step, 0.8 hours per job, and enough capacity for 62 jobs a week. Customers still wait a week because of how templating is scheduled, not because of how long it takes. Templaters book visits only after the deposit clears, which takes two to three days, and they spend about half their time on measuring visits for quotes that have not yet been sold. The week-long wait is a scheduling queue at the front of the process. It is visible to customers, so it gets the complaints, while the queue at the CNC is visible only to the people who walk past the carts.

Goldratt and Cox (2004) made the point that improvements at stations that are not the constraint do not raise output; they only build up inventory in front of the constraint. Adding a third templater would get jobs into the shop sooner, but they would wait longer at the CNC, and the customer would get the countertop on the same day as before.

What Happens When the Constraint Moves

If the CNC's cycle time fell to its 2.5-hour standard, by fixing the program defaults for dark quartz, checking programs before the slab is loaded and staging slabs before the machine is free, capacity would rise to 50 ÷ 2.5 = 20 jobs a week. The CNC would still be the constraint, but output would rise by almost five jobs a week.

If the CNC improved further, for example by running a second shift, the next constraint would be installation at 25 jobs a week. At that point, three crews could not install as many kitchens as the shop could fabricate, and finished tops would wait in the shop instead of in front of the CNC. The bridge saw, at 27.8 jobs a week, would be third. Any plan to raise output well beyond 20 jobs a week therefore needs to consider the installation crews at the same time as the CNC.

Throughput and Work in Process

Hopp and Spearman (2004) argued that the key to controlling a production line is limiting the work in process in front of the bottleneck, because extra jobs there add waiting time without adding output. On the days I counted, an average of 3.8 jobs sat on carts in front of the CNC. At an output rate of 15.2 jobs a week, or about 3 jobs a day, those carts represent more than a working day of waiting for every job that enters. Stevenson (2021) describes this relationship between inventory, throughput and flow time as central to managing a process, and here it accounts for much of the four extra days between promised and actual installation.

Conclusion

The CNC edging machine, at 3.3 hours per job and 15.2 jobs a week, is the shop's constraint. Templating is not, despite the complaints. The improvement work in coming weeks should focus on recovering the CNC's lost 0.8 hours per job, and any larger expansion should be planned together with installation capacity.

References

Goldratt, E. M., & Cox, J. (2004). The goal: A process of ongoing improvement (3rd rev. ed.). North River Press.

Hopp, W. J., & Spearman, M. L. (2004). To pull or not to pull: What is the question? Manufacturing & Service Operations Management, 6(2), 133-148. https://doi.org/10.1287/msom.1030.0028

Stevenson, W. J. (2021). Operations management (14th ed.). McGraw Hill.

Reading the BUSI 3010 Week 4 instructions

The fourth week asks you to identify the constraint in a process using measured cycle times. List each station with its time per unit, account for parallel workers or machines by dividing, and convert each effective cycle time into capacity over a common period. The constraint is the station with the longest effective cycle time, which sets the maximum throughput of the whole process. Check the result against actual output if you can. The paper should then explain what would happen if the constraint improved, naming the next constraint. Many sections also expect a comment on why the station people complain about may not be the real constraint. Tables, short calculations and two to four pages of explanation are typical, with readings on constraints and flow.

How this BUSI 3010 Week 4 example is built

The paper opens with the shop's belief about templating and the question of which station limits weekly output. A method section explains timing 29 jobs at seven stations and the 50-hour week. A table gives each station's measured hours, parallel resources, effective hours and weekly capacity, from templating at 62.5 jobs to the CNC at 15.2. The constraint section matches the CNC figure to actual output and explains the gap between its 3.3-hour measured time and 2.5-hour standard. A section explains the templating wait as a booking queue, citing Goldratt and Cox on improvements away from the constraint. Another shows capacity rising to 20 jobs and installation becoming the next limit. A throughput section counts 3.8 jobs on carts, citing Hopp and Spearman and Stevenson.

BUSI 3010 Week 4 rubric: what earns full marks

Graders reward an analysis led by evidence. The constraint must be identified from effective cycle times, with parallel resources handled correctly; a paper that names the station people complain about without timing it loses most of the credit. Checking the computed throughput against real output is a strong move that confirms the finding. The paper should explain what the constraint implies, including why improving other stations would not raise output. Naming the next constraint and the throughput at which it binds shows understanding of how constraints move. Connecting work in process to waiting time adds depth. Readings should explain specific points, such as the effect of non-bottleneck improvements, rather than appear as general background.

Common BUSI 3010 Week 4 mistakes, and how to avoid them

Time each station for enough units to get a stable average, and record how many people or machines work in parallel at each. Divide to get effective cycle times, then convert to capacity over the same period for every station. The longest effective time is your constraint; check it against actual output. Then ask what happens if it improves, and find the next longest. Common errors include using total process time instead of station times, forgetting to divide by parallel resources and naming the constraint from complaints. Another weakness is stopping at identification without explaining what to do about it. If you would like a model bottleneck analysis for a process you know, share station times and how many people work at each.

Get a BUSI 3010 Week 4 example written to your instructions

Send the Week 4 prompt, the rubric, and the station timings you recorded, and a worked BUSI 3010 bottleneck example returns inside 24-48 hours, first sample free. Timings decide which station constrains the line, so none of them are assumed. The work runs on the numbers you send and stops where those numbers stop.

More BUSI 3010 papers and BS in Business Administration samples

BUSI 3010 Week 4 questions, answered

Where can I find a free BUSI 3010 Week 4 sample paper?

The bottleneck analysis and its seven-station timing table are reproduced in full on this page, free.

Which station is the constraint in the BUSI 3010 Week 4 example?

The CNC edging machine, at 3.3 hours per job, which limits the shop to 15.2 kitchen jobs a week.

Why isn't templating the bottleneck?

Two templaters at 0.8 effective hours per job could handle 62 jobs a week; customers wait because of how visits are booked.

What happens if the CNC improves?

At its 2.5-hour standard it could produce 20 jobs a week, and beyond about 25 the installation crews become the constraint.

How does work in process relate to lead time?

An average of 3.8 jobs waiting on carts in front of the CNC adds more than a working day of waiting to every job.