BUSI 3010 Week 11 Integrated Operations Report Example

Operations Management Walden University Free custom sample in 24 to 48h

This BUSI 3010 Week 11 integrated operations report example pulls a term of work on a composite stone fabrication shop into one argument: lead time is fourteen working days instead of ten because the CNC edging machine is the constraint and loses time to work that need not happen while it is stopped. Walden BUSI 3010 scores the final report on integration, so the sample states its claim first, then uses each earlier analysis as evidence, from the wait in front of the CNC on the process map to the 14.8 percent chip rate on dark quartz. A table shows what each finding contributes. The recommendation sequences three inexpensive changes and sets three measures with dates. As a capstone for the BS in Business Administration course, the report shows eleven assignments becoming one case.

CourseBUSI 3010 Operations Management
WeekWeek 11
Paper typeOperations report
LengthAbout 1,040 words, 6 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramBS in Business Administration
UpdatedOctober 2026

Free sample paper for BUSI 3010 Week 11

1

Fourteen Days Becomes Ten When the CNC Is Treated as the Constraint: An Operations Report on a Stone Fabrication Shop That Draws the Term's Map, Capacity, Bottleneck, Quality, Inventory, Forecast and Layout Work Into One Recommendation

Student Name

Walden University

BUSI 3010: Operations Management

Instructor Name

Month Day, Year

What this page is doingThe title states the report's claim and lists the analyses it rests on, because the report is scored on integration rather than coverage.
2

Fourteen Days Becomes Ten When the CNC Is Treated as the Constraint: An Operations Report on a Stone Fabrication Shop That Draws the Term's Map, Capacity, Bottleneck, Quality, Inventory, Forecast and Layout Work Into One Recommendation

The Claim

Red River Stone & Surface, the composite stone shop followed through this course, promises to install a kitchen countertop ten working days after templating and has averaged fourteen. The shop believes the cause is templating. This report argues that the cause is the CNC edging machine, that the machine loses about a fifth of its time to work that does not need to happen while it is stopped, and that three inexpensive changes, made in a set order, should bring lead time back to ten days through the 2029 summer peak without buying equipment.

What this page is doingThe report opens on a claim about the operation, so each finding that follows is evidence for it rather than a tour of the term.
3

The Evidence

Where Jobs Wait

The process map built early in the term followed four jobs through twenty-one steps and seven lanes. The longest wait between fabrication steps was in front of the CNC, nine to twenty-two working hours, while no other processing wait exceeded three hours. The week-long wait for a templating visit happens before the job reaches the shop floor and is caused by how visits are booked, not by how long templating takes.

How Much the Machine Can Do

The capacity calculation put the CNC's design capacity at 20 jobs a week and its effective capacity at 17, with actual output of 15.2. Utilization was 76.0 percent and efficiency 89.4 percent. Demand in May and June ran at 17 to 18 jobs a week, above effective capacity, which explains why the queue grew in summer.

Which Station Limits Output

Timing 29 jobs at seven stations confirmed the CNC as the constraint. Its measured time of 3.3 hours per job gives 15.2 jobs a week, exactly the shop's actual output. Templating, at 0.8 effective hours per job, could handle 62. Installation, at 25 jobs a week, is the next constraint after the CNC.

Defects That Pass Through the Constraint Twice

The quality analysis found edge chips on 6.0 percent of pieces, rising to 14.8 percent where dark quartz ran at the standard granite speed. Chipped pieces that must be remade go through the CNC a second time, so quality losses also consume constraint hours. The causes were a feed rate set for granite and bit changes tied to the calendar rather than to use.

Supporting Analyses

Three other analyses matter less to the claim but shape the plan. The inventory analysis showed that slab supply is not the problem: an order size of 33 slabs with a reorder point of 18 keeps the best-selling color in stock, and a quantity discount justifies ordering 60 once a second rack is installed. The forecast comparison found that a three-month moving average fits monthly demand better than exponential smoothing, but both run low in spring, so summer capacity should be planned above the forecast. The layout study measured 280 meters of material travel per job and found that moving the polishing benches next to the CNC would cut it to about 212 for $3,500.

Table 1

Findings and What Each Contributes to the Claim

AnalysisKey figureContribution |
Process map9 to 22 hours waiting before the CNCShows where time is lost |
CapacityEffective capacity 17 jobs a week; summer demand 17 to 18Shows why the queue grows in summer |
BottleneckCNC 3.3 hours per job, 15.2 jobs a weekIdentifies the constraint |
Quality14.8 percent chips on dark quartzRework consumes constraint time |
InventoryOrder 33, reorder at 18; 60 with discountRules out slab supply as the cause |
ForecastMoving average error 12 percent, biased lowSummer must be planned above forecast |
Layout280 meters per job; 212 after a partial moveReduces handling near the constraint |

Red River Stone & Surface and all figures are composite.

Recommendation

Make three changes, in this order.

First, stage the next slab and verify its program while the CNC is still cutting, using a part-time material handler and a second monitor, at about $22,000 a year. This targets the 0.6 hours per job lost to crane waits and program checks and should raise CNC capacity to about 18.5 jobs a week.

Second, give each stone type its own cutting speed in the machine's settings and replace bits by distance cut. This costs about $1,800 a year in bits and should cut chips on dark quartz from 14.8 percent toward the 3 percent seen on light quartz, freeing CNC time now spent on remakes.

Third, move the polishing benches to the west wall beside the CNC for about $3,500, reducing handling and the chance of cracking pieces between the CNC and polishing.

The order matters. Goldratt and Cox (2004) argued that improvement should start at the constraint and that gains elsewhere are illusory until the constraint is addressed. The first two changes work directly on the CNC. The third reduces handling after it. Templating changes, a second CNC and the full layout redesign should wait, because none raises output until the CNC's lost time is recovered.

What this page is doingThe recommendation is a sequence, because the changes interact and the order matters.
4

Measures and Dates

Each month the shop will report three figures: CNC hours per job, with a target of 2.8 by March 2029; the dark quartz chip rate, with a target below 5 percent by February 2029; and average working days from templating to installation, with a target of ten or fewer through June 2029. If CNC hours per job fall but lead time does not, the next constraint, installation, should be examined.

Limits of the Analysis

The analyses rest on composite records and short histories: six months of production data, two weeks of timing and eighteen months of sales. Schmenner and Swink (1998) argued that operations performance improves as material moves through a process more swiftly and evenly; the evidence here supports that view for this shop, but the size of the gain should be confirmed by the measures above rather than assumed. Little (1961) showed that waiting time falls when work in process falls at a given output rate, so the count of jobs on carts in front of the CNC is the earliest sign of whether the plan is working.

References

Goldratt, E. M., & Cox, J. (2004). The goal: A process of ongoing improvement (3rd rev. ed.). North River Press.

Little, J. D. C. (1961). A proof for the queuing formula: L = λW. Operations Research, 9(3), 383-387. https://doi.org/10.1287/opre.9.3.383

Schmenner, R. W., & Swink, M. L. (1998). On theory in operations management. Journal of Operations Management, 17(1), 97-113. https://doi.org/10.1016/S0272-6963(98)00028-X

Reading the BUSI 3010 Week 11 instructions

The final assignment brings the term's analysis of one process into a single report. Open with a claim about the operation, then support it with the specific findings from earlier weeks: the process map, the capacity and constraint analysis, the quality findings, and any inventory, forecasting or layout work that bears on it. Earlier calculations should appear as evidence for the claim rather than as a summary of what was completed. The report should end with a recommendation, often a sequence of changes, along with the measures that will show success and the dates by which they should be reached. A brief section on limits is expected. Most sections set five to eight pages, and a summary table linking findings to the claim helps.

How the BUSI 3010 Week 11 example is put together

The report opens with the claim that the CNC, not templating, explains the fourteen-day lead time. Evidence sections follow: the process map's nine to twenty-two hours of waiting in front of the CNC, capacity figures showing summer demand above effective capacity, timing that confirms 15.2 jobs a week at the constraint and chipped dark quartz that sends pieces back through the CNC. A supporting section rules out slab supply, notes the forecast's low bias and cites the layout study. Seven rows of a summary table tie the findings to the claim. The recommendation sequences three changes, staging and program checks, feed rates and bit changes, and moving polishing benches, citing Goldratt and Cox. Measures with dates and a limits section citing Schmenner and Swink and Little close it.

Where the marks sit in the BUSI 3010 Week 11 rubric

The report is scored on integration. A tour of the term's assignments in order, without a claim tying them together, earns far less than a report that uses selected findings as evidence. Graders look for a clear claim near the start and for each section to show how its finding supports or qualifies it. Findings that do not bear on the claim should be brief or left out. Recommendations ought to grow out of the evidence, and when changes depend on each other, their order needs a reason. Measures need targets and dates. Accuracy matters: figures repeated from earlier weeks must match. A limits section that acknowledges short histories or composite data shows maturity. Readings should support the logic of the recommendation, such as starting at the constraint.

Common BUSI 3010 Week 11 mistakes, and how to avoid them

Write your claim in one or two sentences before drafting anything else. Then go through every earlier assignment and ask what each finding says about that claim; keep the ones that support or challenge it and set aside the rest. Order the evidence so the strongest comes first. Turn your earlier improvement ideas into a sequence and explain why the order matters. Set measures with dates. Check every number against your earlier work. Weak reports summarize each week in turn, leave the claim implicit or recommend everything at once. Others introduce new analysis at the last minute. A summary table linking findings to the claim helps both you and the grader. If you need a model operations report for a process you studied this term, share your earlier findings.

Get a BUSI 3010 Week 11 example written to your instructions

Send the Week 11 prompt, the rubric, and the earlier analysis from the term, and a BUSI 3010 report built on that material returns inside 24-48 hours, first sample free. A closing report is assembled out of real work. What arrives draws on the material you send and introduces no finding that was never studied.

More BUSI 3010 papers and BS in Business Administration samples

BUSI 3010 Week 11 questions, answered

Where can I find a free BUSI 3010 Week 11 sample paper?

The complete operations report on the stone fabrication shop, findings table and recommendation included, is free on this page.

What is the claim of the BUSI 3010 Week 11 report?

That lead time slipped from ten to fourteen working days because the CNC is the constraint and loses time to avoidable setup and rework.

Which findings support the claim?

The wait in front of the CNC, capacity below summer demand, a measured throughput of 15.2 jobs and chips that send pieces back through the CNC.

What does the report recommend?

Three changes in order: staging and program checks at the CNC, material-specific feed rates with bit changes by footage, and moving the polishing benches.

How will success be measured?

By CNC hours per job, the dark quartz chip rate and working days from templating to installation, each with a target date.