Stage the Next Slab and Check the Program While the CNC Is Still Cutting: An Improvement Proposal to Move 0.6 Hours of Setup Out of the Constraint's Cycle, Costed at $22,200 a Year, Owned by the CNC Lead and Measured by Hours per Job
Student Name
Walden University
BUSI 3010: Operations Management
Instructor Name
Month Day, Year
Stage the Next Slab and Check the Program While the CNC Is Still Cutting: An Improvement Proposal to Move 0.6 Hours of Setup Out of the Constraint's Cycle, Costed at $22,200 a Year, Owned by the CNC Lead and Measured by Hours per Job
The Problem as the Analysis Found It
The bottleneck analysis earlier in this course found that the edge-profiling CNC at the composite Fargo stone shop limits everything to 15.2 kitchen jobs a week. Its measured cycle time is 3.3 hours per job, against a standard program time of 2.5 hours. Spring sales of 17 to 18 jobs a week outran it, so the queue in front of the CNC grew and installations slipped from ten working days after templating to fourteen.
The 0.8 hours between standard and measured time is not cutting time. Timing showed where it goes: about 0.35 hours per job idle until the crane delivers the following slab section, about 0.25 hours verifying the program on the first piece after the slab is already on the table, and about 0.2 hours of slower feed on dark quartz, which the separate quality changes now in progress will address.
The Change
The proposal is to move the first two of those activities outside the CNC's cutting time. While the CNC is cutting one job, a material handler stages the next job's slab sections on the cart beside it and the CNC lead checks the next program on the second monitor against the slab photo. When the machine finishes, the next job is loaded immediately, and the program has already been verified.
This is the logic Shingo (1985) applied to machine changeovers: sort setup tasks into those that truly need the machine idle and those that do not, then shift the second group into the time the machine is busy. McIntosh et al. (2000) cautioned that the method's gains depend on redesigning the work around the machine rather than simply speeding it up, which is why this proposal adds a person and a monitor rather than asking the operator to hurry.
Expected Effect
Moving 0.35 hours of crane waiting and about 0.25 hours of program checking outside the cycle would bring the CNC's time per job from 3.3 hours to about 2.7 hours. At 50 scheduled hours a week, capacity would rise from 50 ÷ 3.3 = 15.2 jobs to 50 ÷ 2.7 = 18.5 jobs.
That covers the summer peak of about 18 jobs a week, which means the queue in front of the CNC should stop growing in May and June. If the dark quartz feed-rate changes also hold, the remaining 0.2 hours would shrink, and the CNC would approach its standard of 2.5 hours, or 20 jobs a week. At that point the CNC would still be the constraint, with installation the next limit at about 25 jobs a week.
Cost
Table 1
Annual Cost of the Change
| Item | Cost | |
|---|---|
| Part-time material handler, 20 hours a week for 50 weeks at $21.00 loaded | $21,000 | |
| Second monitor and stand at the CNC console | $450 | |
| Training for the handler on gantry crane operation and slab staging | $750 | |
| Total, first year | $22,200 | |
Red River Stone & Surface and its costs are composite. Later years cost about $21,000.
The handler's hours are concentrated in the mornings and early afternoons, when the CNC runs most jobs. Outside those hours the handler sorts remnants in the yard, work currently done by fabricators on overtime.
Return
Each additional job the shop can complete is worth about $1,900 in contribution margin, the sale price of about $4,800 less stone, hardware and direct labor. Last May and June the shop lost 22 quoted jobs in which customers cited the lead time as their reason for going elsewhere. If the change lets the shop complete one additional job a week across the year, a conservative assumption given the summer losses, the contribution is about $95,000 a year against a cost of about $22,000. Even at half a job a week, the change pays for itself more than twice over.
Owner
The CNC lead owns the change. He will write the staging sequence with the handler, set the rule that no slab goes onto the CNC table until its program has been checked on the second monitor, and report the measures below each Monday. The production manager approves the handler's hiring and reviews the results.
How We Will Know It Worked
The primary measure is CNC hours per job, taken from the machine's run log each week. The target is 2.8 hours or less within eight weeks of the handler starting. Two supporting measures follow from it: jobs completed per week, which should rise above 17 in a week when demand is there, and the count of jobs parked beside the CNC at 3 p.m., which should fall from an average of 3.8 to below 2.
If CNC hours per job have not fallen below 3.0 after eight weeks, the change is not working as intended, and the handler's hours should be reassigned before the cost continues. Goldratt and Cox (2004) insisted that time lost at the constraint is lost to the whole plant, and that time saved at other stations buys nothing; this measure tests whether the hours saved are actually at the bottleneck.
What This Proposal Does Not Do
It does not add CNC hours, buy a second machine or move the CNC. Those are larger changes that may be needed if demand keeps growing, but they should wait until this change shows how much capacity the existing machine actually has. Spending on a second machine before recovering the first one's lost hours would buy capacity the shop already owns.
References
Goldratt, E. M., & Cox, J. (2004). The goal: A process of ongoing improvement (3rd rev. ed.). North River Press.
McIntosh, R. I., Culley, S. J., Mileham, A. R., & Owen, G. W. (2000). A critical evaluation of Shingo's 'SMED' (Single Minute Exchange of Die) methodology. International Journal of Production Research, 38(11), 2377-2395. https://doi.org/10.1080/00207540050031823
Shingo, S. (1985). A revolution in manufacturing: The SMED system. Productivity Press.
Reading the BUSI 3010 Week 10 instructions
In Week 10 the course asks for one improvement to the process you have studied, written so that someone could approve it. Open with the problem as your earlier analysis established it, including the figure that showed it. State one change, not a program of several, because a bundle of changes cannot be evaluated or funded clearly. Explain how the change works, estimate its effect on the measure that matters, and show its cost in a table. Name the person who owns it and say what they will do. Finally, name the measure that will judge the change, its target, its deadline and the level at which you would pull back. Three to four pages is common, with readings supporting the method.
Inside the BUSI 3010 Week 10 example
The paper opens with the CNC's measured 3.3 hours per job, the 2.5-hour standard and summer demand above capacity, then breaks the 0.8-hour gap into crane waiting, program checks and slow feed on dark quartz. The change has a material handler stage the next slab and the CNC lead check the next program on a second monitor while the machine cuts, citing Shingo and McIntosh and colleagues. The effect section projects 2.7 hours per job and 18.5 jobs a week. A cost table totals $22,200 for the first year. A return section uses 22 lost summer quotes and $1,900 margin per job. The owner section names the CNC lead, and the measurement section sets a target of 2.8 hours with a stop rule at 3.0, citing Goldratt and Cox.
Where the marks sit in the BUSI 3010 Week 10 rubric
Proposals are graded on feasibility as much as on the idea. The problem should come from earlier analysis, with its figure, so the reader sees why this change was chosen. A single change, clearly described, earns more than several bundled together. The effect estimate must be calculated, not asserted, and the cost should be itemized. Graders look for a named owner with concrete responsibilities, since a change with no owner rarely happens. The measure is critical: it should be specific, with a target and a date, and should be able to show failure as clearly as success. A stop rule shows the writer has thought about what happens if the change does not work. Readings should support the mechanism of the change.
BUSI 3010 Week 10 help: mistakes that cost marks
Go back to your bottleneck or quality analysis and find where the largest avoidable loss sits. Design one change that removes part of that loss, then estimate the new figure with arithmetic. Price the change honestly, including people's time. Name the person who would own it and list what they would do in the first month. Choose one primary measure and set a target, a date and a level at which you would stop. Weak proposals list several improvements, claim savings without calculation or leave ownership to "management." Others choose a measure that cannot show failure. Keep to one change and make it fundable. If you would like a model improvement proposal for a process you have analyzed, share the problem figure and the change you have in mind.
Get a BUSI 3010 Week 10 example written to your instructions
Send the Week 10 prompt, the rubric, and the analysis from earlier in the term that the proposal builds on, and a BUSI 3010 improvement example returns inside 24-48 hours, first sample free. A proposal is only as concrete as the process behind it, so what arrives extends the analysis already done in your section instead of starting from nothing.
More BUSI 3010 papers and BS in Business Administration samples
- BUSI 3010 Week 1: Real Operation Discussion Post
- BUSI 3010 Week 2: Swimlane Process Map
- BUSI 3010 Week 3: CNC Capacity Calculation
- BUSI 3010 Week 4: Bottleneck Analysis
- BUSI 3010 Week 5: Calculation Check Peer Replies
- BUSI 3010 Week 6: Quality Defect Memo
- BUSI 3010 Week 7: EOQ and Reorder Point Analysis
- BUSI 3010 Week 8: Forecast Method Comparison
- BUSI 3010 Week 9: Shop Floor Layout Proposal
- BUSI 3010 Week 11: Integrated Operations Report
BUSI 3010 Week 10 questions, answered
Where can I find a free BUSI 3010 Week 10 sample paper?
The improvement proposal for the shop's CNC, with its cost table and measures, is posted in full and free on this page.
What change does the BUSI 3010 Week 10 proposal make?
Staging the next slab and checking its program while the CNC is still cutting, so the machine no longer waits for either.
How much capacity would it add?
CNC time per job should fall from 3.3 to about 2.7 hours, raising capacity from 15.2 to about 18.5 jobs a week.
What does it cost?
About $22,200 in the first year, mostly a part-time material handler, and about $21,000 a year after that.
How will the shop know if it worked?
CNC hours per job should reach 2.8 or less within eight weeks; if they stay above 3.0, the handler's hours are reassigned.