BUSI 3010 Week 3 CNC Capacity Calculation Example

Operations Management Walden University Free custom sample in 24 to 48h

This BUSI 3010 Week 3 CNC capacity calculation example works out design capacity, effective capacity, utilization and efficiency for the machine that shapes countertop edges at a composite stone fabrication shop. Walden BUSI 3010 marks capacity work as right or wrong, so every input carries a unit and a time base, and each figure appears with its arithmetic: 50 scheduled hours at 2.5 hours per job gives 20 jobs a week, 7.5 hours of planned loss leaves 17, and actual output of 15.2 jobs yields 76.0 percent utilization and 89.4 percent efficiency. The interpretation explains why the efficiency figure matters more, compares the CNC with the saw, polishers and installers, and links summer demand above 17 jobs to a growing queue. For a BS in Business Administration reader, the page is a worked model of showing every step of a capacity figure, with Little and Stevenson behind the reasoning.

CourseBUSI 3010 Operations Management
WeekWeek 3
Paper typeCapacity calculation
LengthAbout 1,000 words, 6 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramBS in Business Administration
UpdatedOctober 2026

Free sample paper for BUSI 3010 Week 3

1

Design Capacity of 20 Jobs a Week, Effective Capacity of 17 and Actual Output of 15.2: A Capacity Calculation for the CNC Edging Machine at a Stone Fabrication Shop, With Utilization and Efficiency Interpreted

Student Name

Walden University

BUSI 3010: Operations Management

Instructor Name

Month Day, Year

What this page is doingThe title states the three capacity figures in order, so a reader can check the arithmetic before reading the interpretation.
2

Design Capacity of 20 Jobs a Week, Effective Capacity of 17 and Actual Output of 15.2: A Capacity Calculation for the CNC Edging Machine at a Stone Fabrication Shop, With Utilization and Efficiency Interpreted

The Resource and Why It Was Chosen

This calculation measures how much the CNC edging machine can produce at Red River Stone & Surface (a composite Fargo fabricator). The CNC shapes the edge profile on each countertop piece and cuts the openings for sinks and cooktops. It was chosen because last week's process map showed that jobs wait longer in front of it than in front of any other machine, sometimes nearly three working days. Capacity here is measured in kitchen jobs per week, where a job is a typical kitchen of about 55 square feet. That unit was chosen because the shop sells, schedules and installs by the job.

What this page is doingThe calculation begins with the resource and its time base, because every later figure depends on them.
3

Inputs

All inputs come from the shop's schedule, the machine's run log and the maintenance record for the 26 weeks from January 5 to July 3, 2028.

Table 1

Inputs for the CNC Capacity Calculation

InputValueUnit and time baseSource |
Scheduled time50Hours per week (10-hour days, 5 days)Shift schedule |
Standard CNC time per job2.5Hours per job, including loading and unloadingMachine program averages |
Tool changes and bit dressing2.0Hours per weekRun log |
Weekly cleaning and maintenance3.0Hours per weekMaintenance record |
First-piece program checks1.5Hours per weekRun log |
Waiting for the gantry crane to move slabs1.0Hours per weekRun log |
Actual jobs completed395Jobs in 26 weeksProduction log |

Red River Stone & Surface and its records are composite.

Calculations

Design capacity is the most the machine could produce if it ran at its standard time for every scheduled hour.

Design capacity = 50 hours per week ÷ 2.5 hours per job = 20.0 jobs per week.

Effective capacity removes the time the shop plans to lose every week. The planned allowances are tool changes (2.0 hours), cleaning and maintenance (3.0 hours), first-piece checks (1.5 hours) and crane waits (1.0 hour), which total 7.5 hours.

Effective available time = 50.0 − 7.5 = 42.5 hours per week.

Effective capacity = 42.5 hours per week ÷ 2.5 hours per job = 17.0 jobs per week.

Actual output is the average over the 26 weeks.

Actual output = 395 jobs ÷ 26 weeks = 15.2 jobs per week.

Utilization compares actual output with design capacity.

Utilization = 15.2 ÷ 20.0 = 0.76, or 76.0 percent.

Efficiency compares actual output with effective capacity.

Efficiency = 15.2 ÷ 17.0 = 0.894, or 89.4 percent.

What this page is doingEach figure is computed on its own line with the arithmetic visible.
4

What the Figures Mean

The two percentages answer different questions. Utilization of 76 percent says the machine produces about three-quarters of what it could if nothing were ever lost. That figure looks modest, and it would lead a casual reader to conclude the CNC has spare capacity. It does not. Most of the gap between design and effective capacity, 3 jobs a week, is planned loss that the shop has chosen to accept: bits must be changed, the machine must be cleaned, and the first piece of each program must be checked.

Efficiency of 89.4 percent is the more useful measure for management, because it compares output with what the machine can realistically produce. The remaining gap, 1.8 jobs a week, comes from losses nobody planned: programs that had to be rerun, an operator called away to help unload a delivery and pieces that arrived at the CNC late in the day with too little shift left to finish them.

The figures matter because of demand. Over the same 26 weeks, the shop took orders for an average of 15.2 jobs a week, so output kept up with orders on average. But orders are seasonal. In May and June the shop sold about 17.3 and 18.2 jobs a week, above the CNC's effective capacity of 17. When demand exceeds effective capacity, the queue in front of the machine grows every week until demand falls, which is consistent with the carts seen there and with installation lead times that slipped from ten working days to fourteen.

Comparison With Other Stations

The same method applied to the other fabrication steps gives a rough sense of where the CNC stands. The bridge saw has a standard time of about 1.8 hours per job, for a design capacity near 27.8 jobs a week on the same 50 hours. The two polishers together have 100 scheduled hours and need about 2.2 hours per job, for about 45 jobs a week. The three installation crews have 150 crew hours a week and average about 6 hours per job including travel, for about 25 jobs a week. On these figures, the CNC has the lowest capacity of the fabrication and installation steps, which next week's bottleneck analysis will test with measured cycle times.

Assumptions and Limits

The calculation assumes that a typical kitchen job is a reasonable unit. Large jobs with islands take longer on the CNC, and small vanity tops take less, so a month with many large jobs would lower the real capacity. It also assumes that the standard time of 2.5 hours, taken from program averages, is accurate; if operators routinely slow the feed rate on dark quartz to prevent chipping, the true standard is higher. Stevenson (2021) notes that effective capacity depends on product mix, quality requirements and scheduling, all of which apply here. The queuing law proved by Little (1961) ties waiting to inventory: with output fixed, the time a job spends in the shop grows with the number of jobs ahead of it, so every extra job waiting in front of the CNC adds directly to the customer's lead time when output is fixed. Schmenner and Swink (1998) argue that productivity rises as material moves more swiftly and evenly through a process, and the CNC is where this shop's flow is least even.

References

Little, J. D. C. (1961). A proof for the queuing formula: L = λW. Operations Research, 9(3), 383-387. https://doi.org/10.1287/opre.9.3.383

Schmenner, R. W., & Swink, M. L. (1998). On theory in operations management. Journal of Operations Management, 17(1), 97-113. https://doi.org/10.1016/S0272-6963(98)00028-X

Stevenson, W. J. (2021). Operations management (14th ed.). McGraw Hill.

The Walden BUSI 3010 Week 3 instructions

Week 3 is the course's first calculation that can be marked wrong. You are asked to compute design capacity, effective capacity and actual output for one resource, then utilization and efficiency, and to interpret what the figures mean. Every input needs a unit and a time base, such as hours per week or jobs per hour, and should come from a stated source. Show each calculation on its own line with the arithmetic visible, so a grader can check it in a minute. Utilization divides output by design capacity and efficiency divides it by effective capacity; swapping the denominators is where most submissions slip. The interpretation should say what the numbers imply for the operation, and a short note on assumptions helps. Two to four pages is usual.

Inside the BUSI 3010 Week 3 example

The paper explains why the CNC was chosen and why capacity is measured in kitchen jobs per week. A table lists seven inputs with values, units and sources, from 50 scheduled hours to 395 jobs completed in 26 weeks. The calculations appear line by line: design capacity of 20 jobs, effective available time of 42.5 hours, effective capacity of 17 jobs, actual output of 15.2, utilization of 76.0 percent and efficiency of 89.4 percent. The interpretation separates planned loss from unplanned loss and ties summer demand of 17 to 18 jobs a week to the growing queue. A comparison section estimates capacity at the saw, polishers and installation crews. A final section lists assumptions about job size and standard time, citing Stevenson, Little and Schmenner and Swink.

Reading the BUSI 3010 Week 3 rubric

Accuracy carries most of the weight. Inputs without units, figures that do not reconcile, or utilization computed against effective capacity all cost marks that clear writing cannot recover. Graders look for each formula, its substitution and its result, in that order. Planned allowances should be listed individually so the reader can see what separates design from effective capacity. Interpretation earns the remaining credit: the strongest papers explain what each percentage means for decisions and connect capacity to demand, showing when a queue will grow. Comparing the resource with others in the process shows judgment about where the constraint lies. Naming assumptions, such as product mix and how accurate the standard time is, earns the final marks.

Common BUSI 3010 Week 3 mistakes, and how to avoid them

Pick one resource and decide on a unit of output your organization actually uses. Gather scheduled time, the standard time per unit, every planned loss and actual output over a stated period. Write each input in a table with its unit and source. Then calculate design capacity, effective capacity, utilization and efficiency on separate lines. Check that utilization is lower than efficiency; if not, the bases are probably reversed. Weak submissions skip units, round too early, or report a percentage with no interpretation. Another common gap is ignoring demand, which is what makes capacity matter. If you would like a model capacity calculation for a resource at your workplace, send its schedule, standard time and recent output.

Get a BUSI 3010 Week 3 example written to your instructions

Send the Week 3 prompt, the rubric, and the operating figures the classroom supplied or the ones from the process being studied, and a worked BUSI 3010 capacity example returns inside 24-48 hours, first sample free. Where a figure is missing, the example states the assumption rather than inventing a number.

More BUSI 3010 papers and BS in Business Administration samples

BUSI 3010 Week 3 questions, answered

Where can I find a free BUSI 3010 Week 3 sample paper?

The complete CNC capacity calculation, inputs table and interpretation included, is posted on this page for free.

What is the design capacity in the BUSI 3010 Week 3 example?

Twenty kitchen jobs a week: 50 scheduled hours divided by a standard time of 2.5 hours per job.

How is effective capacity found?

By subtracting 7.5 hours a week of planned losses, such as tool changes, cleaning and program checks, then dividing 42.5 hours by 2.5.

What are utilization and efficiency?

Utilization is actual output over design capacity, 76.0 percent; efficiency is actual output over effective capacity, 89.4 percent.

Why does the queue grow in summer?

Demand in May and June ran at 17 to 18 jobs a week, above the machine's effective capacity of 17.