BUSI 3010 Week 7 EOQ and Reorder Point Analysis Example

Operations Management Walden University Free custom sample in 24 to 48h

This BUSI 3010 Week 7 EOQ and reorder point analysis example sets order quantity and reorder point for the best-selling white quartz at a composite countertop shop, then tests the answer against conditions the basic model ignores. Walden BUSI 3010 marks inventory work on auditable arithmetic and stated assumptions, so the sample lists every input with its unit and period, shows the formula, substitution and result for an economic order quantity of 33 slabs and a reorder point of 18 with 95 percent service, and confirms ordering and holding costs nearly match. It then prices a 3 percent discount at 60 slabs, saving about $16,700 a year, against a 40-slab rack, and recommends a second rack and quarterly review. The worked EOQ example carries on past the formula, which is where a BS in Business Administration paper usually earns its best marks.

CourseBUSI 3010 Operations Management
WeekWeek 7
Paper typeInventory analysis
LengthAbout 990 words, 6 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramBS in Business Administration
UpdatedOctober 2026

Free sample paper for BUSI 3010 Week 7

1

How Many Slabs of the Best-Selling Quartz to Order and When: An Economic Order Quantity of 33, a Reorder Point of 18 and Why a 3 Percent Discount at 60 Slabs Changes the Answer Once Rack Space Is Counted

Student Name

Walden University

BUSI 3010: Operations Management

Instructor Name

Month Day, Year

What this page is doingThe title gives both computed figures and the finding that overturns the basic model, which is the analysis the week rewards.
2

How Many Slabs of the Best-Selling Quartz to Order and When: An Economic Order Quantity of 33, a Reorder Point of 18 and Why a 3 Percent Discount at 60 Slabs Changes the Answer Once Rack Space Is Counted

The Item and the Question

Red River Stone & Surface stocks about forty colors of quartz and granite. One color, a white quartz with gray veining, outsells every other and accounts for roughly a third of the shop's slab use. This analysis calculates how many slabs of that color to order at a time and at what stock level to reorder, then tests the result against the conditions the basic model ignores.

What this page is doingThe item and its demand are fixed before any formula, so every input has a unit and a period.
3

Inputs

Table 1

Inputs for the White Quartz Slab

InputSymbolValueUnit and period |
Annual demandD520Slabs per year |
Cost per orderS$240Dollars per order (delivery charge and receiving labor) |
Unit priceP$1,150Dollars per slab |
Annual holding ratei20Percent of price per year |
Holding costH = iP$230Dollars per slab per year |
Working daysN250Days per year |
Lead timeL6Working days from order to delivery |
Standard deviation of daily demandσd1.2Slabs per day |

Red River Stone & Surface and its figures are composite; demand is from 2027 usage records.

The holding rate of 20 percent covers the cost of money tied up in stone, insurance, and the risk of slabs being chipped or cracked while stored. Both the holding cost and the demand are expressed per year so that the formula is consistent.

Economic Order Quantity

Ordering often raises delivery charges, and ordering rarely raises the cost of stone sitting in the yard; the economic order quantity finds the size where the two are equal (Harris, 1990).

EOQ = √(2DS ÷ H)

EOQ = √(2 × 520 × 240 ÷ 230)

EOQ = √(249,600 ÷ 230) = √1,085.2 = 32.9, rounded to 33 slabs.

At 33 slabs per order, the shop would place 520 ÷ 33 = 15.8 orders a year.

Annual ordering cost = 15.8 × $240 = $3,782.

Annual holding cost = (33 ÷ 2) × $230 = $3,795.

Total annual inventory cost = $7,577.

The two costs are nearly equal, as they should be at the economic order quantity.

What this page is doingEach calculation shows the formula, the substitution and the result on separate lines.
4

Reorder Point

Daily demand is d = 520 ÷ 250 = 2.08 slabs per day.

Demand during lead time = 2.08 × 6 = 12.5 slabs.

Daily demand varies, so the shop needs safety stock to avoid running out while an order is on its way. The shop wants to run short no more than about one cycle in twenty, which sets z at 1.65.

Safety stock = z × σd × √L = 1.65 × 1.2 × √6 = 4.85, rounded to 5 slabs.

Reorder point = 12.5 + 4.85 = 17.3, rounded up to 18 slabs.

When the rack holds 18 slabs of this color, the programmer places an order for 33.

What the Model Assumes

The economic order quantity rests on assumptions that should be checked before the answer is used. It assumes demand is steady through the year; in this shop it is not, since summer months run about 40 percent above winter months. It assumes the cost per order and the price do not change with order size. It assumes each order arrives all at once and that there is space to store it. Silver et al. (2017) note that the total cost curve is flat near the optimum, so small departures from the computed quantity cost little, which makes the result robust to modest errors in the inputs. But the assumptions about price and space matter more here.

The Discount the Model Leaves Out

The distributor offers 3 percent off the slab price on orders of 60 slabs or more. At 60 slabs the price falls to $1,115.50 and the holding cost to $223.10 per slab per year.

Table 2

Annual Cost at 33 and at 60 Slabs per Order

Order sizeOrdering costHolding costPurchase costTotal |
33 slabs at $1,150$3,782$3,795$598,000$605,577 |
60 slabs at $1,115.50$2,080$6,693$580,060$588,833 |

Purchase cost is annual demand times unit price.

Ordering 60 slabs at a time saves about $16,700 a year, almost all of it from the lower price. The basic model, which treats price as fixed, cannot see this.

The Constraint the Model Leaves Out

The A-frame rack for this color holds 40 slabs. At the economic order quantity, the most on hand at once is about 33 plus 5 of safety stock, or 38, which fits. At 60 slabs, peak stock would reach about 65, which does not fit. A second A-frame rack costs about $4,500 installed and would take floor space in the slab yard that is now used to stage remnants.

The space constraint therefore turns the decision into a comparison of the discount against the rack. Even after paying for the rack once, the discount would save about $12,200 in the first year and $16,700 in each year after. The larger order also ties up about $15,000 more in stone on average, and it increases the risk that slabs are damaged in storage or left over if the color falls out of fashion.

Recommendation

Order this color 60 slabs at a time, with a reorder point of 18 slabs plus the time needed to receive the larger load, and install a second rack before the next order. Review the decision quarterly: if monthly demand falls below about 30 slabs for two quarters, return to orders of 33. For colors without a discount and with steady demand, the basic economic order quantity remains a sound starting point. Stevenson (2021) cautions that quantity discounts require comparing total cost, including purchases, at each price break, which is exactly where the basic answer and the better answer diverge here.

References

Harris, F. W. (1990). How many parts to make at once. Operations Research, 38(6), 947-950. https://doi.org/10.1287/opre.38.6.947 (Original work published 1913)

Silver, E. A., Pyke, D. F., & Thomas, D. J. (2017). Inventory and production management in supply chains (4th ed.). CRC Press.

Stevenson, W. J. (2021). Operations management (14th ed.). McGraw Hill.

What the BUSI 3010 Week 7 instructions ask for

Week 7 asks for an inventory analysis of one item: the order quantity and reorder point derived from stated demand and cost figures. List each input with a unit and period, keeping holding cost consistent with demand, for example both per year. Show the formula, the substitution and the result on separate lines for the economic order quantity, then for demand during lead time, safety stock and the reorder point. Report the resulting annual ordering and holding costs. The second half of the paper should state the model's assumptions, such as steady demand and fixed prices, and test whether they hold for your item, adjusting the answer where they do not. Two to four pages, with tables for inputs and comparisons, is common.

How this BUSI 3010 Week 7 example is built

The paper introduces the white quartz that makes up about a third of slab use. A table lists eight inputs, including annual demand of 520 slabs, $240 per order, a $1,150 price, a 20 percent holding rate, six days of lead time and a daily standard deviation of 1.2 slabs. Calculations give an economic order quantity of 33, 15.8 orders a year, ordering and holding costs of about $3,780 and $3,795, safety stock of 5 and a reorder point of 18. An assumptions section notes seasonal demand and cites Silver and colleagues on the flat cost curve. A cost table compares orders of 33 and 60 at the discount price. A space section weighs the 40-slab rack against a $4,500 second rack, and the recommendation cites Stevenson.

BUSI 3010 Week 7 rubric: what earns full marks

Inventory papers are graded first on arithmetic. Every input needs a unit and a period, holding cost must match the demand period, and each formula should appear with its substitution so a grader can follow it. A reorder point that ignores lead-time variability, or a safety stock with no service level, loses credit. The second area is reasoning about the model. Graders reward papers that state the assumptions and test them against the item's real conditions, such as seasonality, quantity discounts and storage limits, because the basic answer is often not the best one. Comparing total cost, including purchases, at each price break shows correct handling of discounts. A recommendation that accounts for practical constraints shows business judgment beyond the formula.

Common BUSI 3010 Week 7 mistakes, and how to avoid them

Choose one item with reasonably steady use and gather a year of demand, the cost of placing an order, the unit price and a holding rate. Convert everything to the same period. Calculate the economic order quantity, then lead-time demand, safety stock and the reorder point, showing each step. Then ask what the model assumes and whether your item meets those assumptions: Is demand seasonal? Is there a discount? Is there room to store the order? Adjust and compare total costs. Weak papers mix monthly and annual figures, skip safety stock or treat the formula's answer as final. Others ignore discounts entirely. If you would like a model inventory analysis for an item your organization stocks, share its demand, costs and lead time.

Get a BUSI 3010 Week 7 example written to your instructions

Send the Week 7 prompt, the rubric, and the demand and cost figures the classroom supplied, and a worked BUSI 3010 inventory example returns inside 24-48 hours, first sample free. Where an input is missing, the example labels the assumption rather than filling the gap with an invented figure.

More BUSI 3010 papers and BS in Business Administration samples

BUSI 3010 Week 7 questions, answered

Where can I find a free BUSI 3010 Week 7 sample paper?

This page reproduces the full slab inventory analysis, both tables and the discount comparison, free to read.

What is the economic order quantity in the BUSI 3010 Week 7 example?

Thirty-three slabs per order, from annual demand of 520, an ordering cost of $240 and a holding cost of $230 per slab per year.

How is the reorder point calculated?

Lead-time demand of 12.5 slabs plus safety stock of about 5 at a 95 percent service level, rounded up to 18 slabs.

Why does the discount change the answer?

Ordering 60 slabs at 3 percent off saves about $16,700 a year in total cost, far more than the extra holding cost.

What constraint does the basic model ignore?

Rack space: the current rack holds 40 slabs, so the larger order requires a second rack costing about $4,500.