DDBA 8560 Week 9 Sequenced Implementation Plan Example

Seminar in Healthcare Managerial Decision Making Walden University Free custom sample in 24 to 48h

This DDBA 8560 Week 9 sequenced implementation plan example turns evening MRI hours at Brookfield into eleven steps ordered by seven clearances. Walden DDBA 8560 asks students to connect owners and dates through logic, and the plan applies Pressman and Wildavsky's arithmetic of joint action: if each clearance has a 90 percent chance of timely success, all seven succeed only about 48 percent of the time. Its table gives each step a responsible role, predecessors, a start written as a condition and a column marking the last point where withdrawal is cheap, step six, recruiting technologists and hiring front desk staff. Nilsen's taxonomy explains why the plan is a process model and uses Damschroder and colleagues' Consolidated Framework only as a checklist in this DBA plan.

CourseDDBA 8560 Seminar in Healthcare Managerial Decision Making
WeekWeek 9
Paper typeImplementation plan
LengthAbout 780 words, 5 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramDoctor of Business Administration (DBA)
UpdatedOctober 2026

Free sample paper for DDBA 8560 Week 9

1

Seven Clearances, Eleven Steps: An Implementation Plan for Evening MRI Hours at Brookfield That Applies the Arithmetic of Joint Action, Orders Each Step by Its Dependencies and Marks Where Withdrawal Is Still Cheap

Student Name

Walden University

DDBA 8560: Seminar in Healthcare Managerial Decision Making

Instructor Name

Month Day, Year

What this page is doingThe title counts the clearances and steps and names the plan's two organizing ideas, joint action and cheap withdrawal.
2

Seven Clearances, Eleven Steps: An Implementation Plan for Evening MRI Hours at Brookfield That Applies the Arithmetic of Joint Action, Orders Each Step by Its Dependencies and Marks Where Withdrawal Is Still Cheap

The Chosen Option and Its Clearances

The option chosen for implementation is a four-hour evening session on Brookfield's 3 tesla scanner on four nights each week. The consent map identified five parties whose agreement is required. Two of them must clear the option twice, so the plan requires seven separate clearances: the radiology group's contract amendment for evening reading blocks; the radiology group's approval of which protocols may run in the evening; the technologists' bargaining unit's side letter on voluntary evening shifts; the budget holder's operating approval; the budget holder's approval of two added front desk positions through position control; the MRI safety officer's sign-off on evening safety staffing; and the central scheduling office's template release.

What this page is doingThe plan restates the option and counts its clearances before listing any step, since the count drives the plan's risk.
3

The Arithmetic of Joint Action

Pressman and Wildavsky (1973) followed a 1960s federal jobs program in a California city and showed that a program requiring many separate agreements can fail even when every party supports it, because the probability that all agreements hold is the product of the individual probabilities. Applied here: if each of the seven clearances has a 90 percent chance of being obtained on time, the chance that all seven are obtained on time is about 48 percent. At 95 percent each, it is about 70 percent. The lesson is not pessimism but sequencing. Steps that depend on many prior clearances should not be started until those clearances are in hand, and the plan should keep the option of withdrawing cheaply for as long as possible.

The Sequence

[after]

Dates are written as conditions rather than calendar dates, because the plan's timing depends on clearances whose timing no one controls.

Table 1

Implementation Steps

StepResponsible rolePredecessorEarliest startCheap withdrawal |
1. Propose evening reading block termsImaging directorNoneOn approval of the optionYes |
2. Sign contract amendment and evening protocol listRadiology group president1When terms are agreedYes |
3. Negotiate side letter on voluntary evening shiftsHuman resources labor relations leadNoneOn approval of the optionYes |
4. Confirm evening safety staffing planMRI safety officer3When side letter is signedYes |
5. Approve operating budget and positionsDepartment budget holder2, 4When reading cost and staffing are fixedYes |
6. Recruit technologist volunteers and hire front desk staffImaging manager5When budget is approvedLast cheap point |
7. Train evening staff in safety screeningMRI safety officer6When staff are hiredNo |
8. Build and release evening templatesCentral scheduling supervisor2, 5When protocols and budget are fixedNo |
9. Connect evening reports to referring clinics' recordsInformation systems analyst2When protocols are fixedNo |
10. Inform referring clinics and patientsImaging manager8, 9When templates are liveNo |
11. First evening sessionImaging manager7, 10When all prior steps are completeNo |

Where Withdrawal Is Still Cheap

Through step 5, withdrawal costs only staff time spent on negotiation. Step 6 is the last cheap point: once technologists have rearranged their lives around evening shifts and front desk staff are hired, stopping would cost money and goodwill. The plan therefore holds step 6 until steps 2, 4 and 5 are complete, even if that delays the first session.

What this page is doingThe withdrawal column tells the decision maker when stopping costs little and when it begins to cost a lot.
4

What a Delay Would Do

If the radiology group's amendment, step 2, slips by four weeks, steps 5, 8 and 9 slip with it, and every later step follows. If the side letter, step 3, slips, steps 4 through 7 slip, but templates can still be built. The table's predecessor column lets the manager see these effects before they happen.

The Framework Used

Nilsen (2015) set apart process models, which lay out the stages by which a decision is put into effect, from determinant frameworks, which list factors that help or hinder implementation. This plan is a process model. It uses the Consolidated Framework for Implementation Research, a determinant framework developed by Damschroder et al. (2009), only as a checklist: its attention to the inner setting and to the characteristics of individuals prompted the plan to include staff volunteers and safety training. Calling the framework the plan's structure would misdescribe it.

Communication

Each clearance, once obtained, will be reported to the decision group in writing within a week, so that later steps start from confirmed agreements rather than assumed ones.

Limits

Probabilities of 90 and 95 percent are illustrative. The plan assumes the radiology group will negotiate in good faith.

References

Damschroder, L. J., Aron, D. C., Keith, R. E., Kirsh, S. R., Alexander, J. A., & Lowery, J. C. (2009). Fostering implementation of health services research findings into practice: A consolidated framework for advancing implementation science. Implementation Science, 4, Article 50. https://doi.org/10.1186/1748-5908-4-50

Nilsen, P. (2015). Making sense of implementation theories, models and frameworks. Implementation Science, 10, Article 53. https://doi.org/10.1186/s13012-015-0242-0

Pressman, J. L., & Wildavsky, A. (1973). Implementation. University of California Press.

The Walden DDBA 8560 Week 9 instructions

Week 9 asks for an implementation plan for your chosen option. Restate the option and count the separate clearances it requires. Apply research on joint action to show what that count means for the plan's chance of staying on time. Build a step table with a responsible role, predecessors, a conditional start and a column marking where withdrawal remains cheap. Explain what a delay at key steps would do to later ones. Identify the kind of implementation model you are using and how any framework fits. State your assumptions about probabilities and cooperation. Keep the plan near five pages, with the step table spanning the middle and short sections around it.

Inside the DDBA 8560 Week 9 example

The sample lists seven clearances, including the radiology group's contract amendment and protocol list, the bargaining unit's side letter, budget and position approval, the safety officer's sign-off and template release. The arithmetic section shows about 48 percent at 90 percent per clearance and about 70 percent at 95. The table runs from proposing reading terms to the first evening session. The withdrawal section holds recruitment until reading terms, safety staffing and budget are secured. The delay section traces a four-week slip in the radiology amendment through budget, templates and report delivery. A framework section explains that the plan is a process model and uses the Consolidated Framework only to check for missed determinants.

Reading the DDBA 8560 Week 9 rubric

Owners and dates are expected; what separates bands is the logic connecting them. A plan listing tasks in calendar order with names beside them meets the basic row and goes no further. Marks gather around the dependency structure, and a table in which one delay would not visibly move later steps has hidden how the plan behaves. The joint-action section scores best when the arithmetic uses the plan's own clearances. The framework section tests whether the writer knows what kind of model is in use; calling a determinant framework the plan's structure misdescribes it. A withdrawal column that changes at a clearly reasoned point shows the writer understands the cost of irreversibility.

DDBA 8560 Week 9 help: mistakes that cost marks

Begin by counting clearances from your consent map; each agreement is one. Multiply plausible success rates to see the combined chance. Then order steps so that costly or irreversible ones wait for the clearances they depend on. Write start conditions rather than calendar dates where timing depends on others. Mark the last cheap exit clearly. Read Nilsen's taxonomy before naming a framework. Keep each step to one action and one owner. Check that every predecessor listed actually must come first. Report each clearance in writing once obtained, so later steps start from confirmed agreements rather than hopes. A short paragraph on what happens if the first clearance fails outright, rather than slipping, makes the plan more honest about its risks.

Get a DDBA 8560 Week 9 example written to your instructions

Bring the consent map or stakeholder brief from Week 8 alongside the Week 9 prompt and rubric, and a dependency-ordered plan comes back inside 24 to 48 hours, the first free. Steps are assigned to roles, not to named colleagues, which keeps the plan usable beyond your own department.

More DDBA 8560 papers and DBA samples

DDBA 8560 Week 9 questions, answered

Where can I find a free DDBA 8560 Week 9 sample paper?

All eleven steps of the Brookfield rollout, with owners and predecessors, are published here free.

How many clearances does the DDBA 8560 Week 9 plan require?

Seven, from the radiology group's contract amendment to the scheduling office's template release.

What does the joint-action arithmetic show?

At 90 percent per clearance, all seven succeed on time only about 48 percent of the time.

Where is the last cheap point to withdraw?

Step six, recruiting technologist volunteers and hiring front desk staff.

Why are dates written as conditions?

Timing depends on clearances whose dates no one on the project controls.