Pricing Eleven Risks: An Expected Value of About $413,000 for the Loan Servicing Consolidation, With Every Probability and Cost Sourced and a Three-Point Estimate on the $435,000 Escrow Line
Student Name
Walden University
WMBA 6623: Enterprise and Project Risk Management
Instructor Name
Month Day, Year
Pricing Eleven Risks: An Expected Value of About $413,000 for the Loan Servicing Consolidation, With Every Probability and Cost Sourced and a Three-Point Estimate on the $435,000 Escrow Line
Assumptions and Sources
This analysis puts a dollar figure on the eleven largest threats to the servicing consolidation at Lakeshore Community Bank (composite). Probabilities are the chance the event occurs before the project closes, with planned responses in place. They come from the project's calibrated scoring session, converted from scale ranges to single figures, and from the bank's 2019 conversion records where those apply. Costs are what the event would cost the bank if it occurred.
Four sources support the cost figures. The cost of correcting a servicing error on one account, about $125 including staff time, refunds and borrower calls, comes from the bank's 2019 conversion, where cleanup of 2,140 accounts cost about $268,000. Temporary staffing premiums come from a staffing agency's written quote of $18 an hour above the bank's wage. Schedule delay costs about $35,000 a week, the project's average weekly spending on staff, vendors and space during the cutover phase. Regulatory restitution and legal costs for loss mitigation errors, about $25,000 per affected case, come from the compliance officer's review of recent enforcement settlements involving similar violations.
Expected Value Table
Table 1
Expected Monetary Value by Risk
| ID | Risk event | Probability | Cost if it occurs | Expected value | |
|---|---|---|---|---|
| R02 | Escrow analysis errors without the analyst's knowledge | 25% | $435,000 | $108,750 | |
| R04 | Center short of 20 staff at cutover | 40% | $132,000 | $52,800 | |
| R10 | Cutover-quarter escrow analyses wrong | 20% | $225,000 | $45,000 | |
| R11 | Loss mitigation files mishandled | 15% | $250,000 | $37,500 | |
| R01 | Local configuration settings missed | 30% | $120,000 | $36,000 | |
| R07 | Vendor conversion team unavailable, three weeks' delay | 30% | $105,000 | $31,500 | |
| R05 | Key staff leave early | 50% | $60,000 | $30,000 | |
| R20 | Lease buildout late | 30% | $90,000 | $27,000 | |
| R06 | Payment routing notice late | 5% | $300,000 | $15,000 | |
| R13 | Paper documents lost | 10% | $150,000 | $15,000 | |
| R09 | Borrower notices late or incomplete | 5% | $280,000 | $14,000 | |
| Total | Eleven priced risks | See rows | See rows | $412,550 | |
Probabilities assume planned responses are in place; costs are composite estimates.
The total expected value, about $413,000, is the average cost these risks would add across many projects like this one. It does not predict the outcome of this particular project. In practice, most of these events will not occur, and one or two may cost far more than their expected value.
Three-Point Estimate on the Largest Line
R02's cost depends on how many accounts are affected. The optimistic case, about $180,000, assumes errors are caught in the first statement cycle on about 1,000 accounts. The most likely case, $435,000, assumes 3,000 accounts and a regulatory examination comment requiring a $60,000 remediation review. The pessimistic case, about $900,000, assumes errors on 6,000 accounts and a formal examination finding with restitution.
Using the weighted average common in project estimating, (optimistic + 4 x most likely + pessimistic) / 6, the mean is about $470,000, higher than the most likely figure because the range is skewed toward larger losses. The standard deviation, approximated as (pessimistic minus optimistic) / 6, is about $120,000. The PMBOK Guide describes this three-point approach as a way to reflect uncertainty in an estimate (Project Management Institute, 2017). Applying the 25 percent probability to the mean gives an expected value of about $117,500 for R02, slightly above the table's figure.
What the Numbers Show
Two observations follow. First, R02 alone carries about a quarter of the total expected value, and its pessimistic case is about three times the combined expected value of all the other lines. Spending to reduce its probability, for example a third trained analyst, is likely worth more than spreading effort across smaller risks. Second, the two lowest-probability lines, R06 and R09, have the largest costs if they occur. Their small expected values understate how much damage either would do, which is why the contingency analysis will treat them separately.
Kwak and Ingall (2007) describe Monte Carlo simulation as a way to combine distributions like these into a range of total outcomes, rather than a single sum. Hubbard (2020) makes a similar argument for replacing point estimates with ranges. A simulation using the three-point ranges would show the probability that total risk costs exceed any given contingency, and it is the next step if the steering committee wants more than the expected value.
References
Hubbard, D. W. (2020). The failure of risk management: Why it's broken and how to fix it (2nd ed.). Wiley.
Kwak, Y. H., & Ingall, L. (2007). Exploring Monte Carlo simulation applications for project management. Risk Management, 9(1), 44-57. https://doi.org/10.1057/palgrave.rm.8250017
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.).
What the WMBA 6623 Week 6 instructions ask for
The quantitative analysis assignment asks students to price risks in dollars. Instructors expect a short, dense document centered on a calculation table listing each risk event with a probability, a cost impact and an expected value, totaled at the foot. Above the table, a paragraph states assumptions in plain sentences and sources each number. Below it, a three-point estimate on the largest line shows optimistic, most likely and pessimistic figures and a weighted result. Strong papers explain what the total means and does not mean and identify risks whose expected values understate their potential damage. Probabilities should reflect planned responses where those are already approved, and the paper should say so. Costs should be what the organization would actually pay.
How this WMBA 6623 Week 6 example is built
The paper states how probabilities and costs were derived and names four sources for costs. A table lists eleven risks with probability, cost and expected value, totaling about $412,550. A paragraph explains that the total is an average across many projects, not a forecast. A three-point estimate for the escrow risk describes each case, computes the weighted mean and standard deviation and cites the PMBOK Guide. A section notes that the escrow risk carries a quarter of the expected value and that two low-probability risks have the largest costs if they occur. A closing paragraph cites Kwak and Ingall and Hubbard on simulation and ranges. Margin comments flag the sourced assumptions and the three-point estimate.
Reading the WMBA 6623 Week 6 rubric
Graders reward probabilities and costs that are sourced and stated as assumptions a reader can check. An accurate expected value table with a correct total carries significant weight. A three-point estimate with correctly computed mean and spread demonstrates technique. Explaining what expected value does not capture, especially for rare, severe events, shows judgment. Pointing toward simulation or ranges as a next step shows awareness of better methods. Expected values that tie back to the stated probabilities and impacts, row by row, protect the marks for accuracy. Analyses that state clearly what the expected value total does and does not mean show the strongest understanding. Labeling estimates as estimates is also part of good practice.
WMBA 6623 Week 6 help: mistakes that cost marks
For each risk, decide what it would cost if it happened and find a source for that number, such as past incidents, quotes or rates. Estimate the probability with your scoring scale or historical data. Multiply and total. For the largest line, estimate best, likely and worst cases and compute the weighted mean. Students often lose marks by giving numbers without sources, by treating the total as a prediction or by skipping the three-point estimate. Another frequent gap is ignoring rare events with very large costs. Flag them. If you need a custom sample quantitative analysis for your project, send us your risk register.
Get a WMBA 6623 Week 6 example written to your instructions
Give the desk the Week 6 prompt, the rubric, and any figures your section supplied, and the analysis comes back with its assumptions listed, its arithmetic shown line by line, and a sensitivity pass at the end. First sample free, 24-48 hours, formatted so every number in the prose points at a cell in the table.
More WMBA 6623 papers and MBA samples
- WMBA 6623 Week 1: Named Risk Discussion Post
- WMBA 6623 Week 2: Project Risk Identification Table
- WMBA 6623 Week 3: Project Risk Register
- WMBA 6623 Week 4: Qualitative Risk Scoring Matrix
- WMBA 6623 Week 5: Risk Score Challenge Replies
- WMBA 6623 Week 7: Risk Response Plan
- WMBA 6623 Week 8: Risk Contingency Reserve Brief
- WMBA 6623 Week 9: Risk Appetite Governance Memo
- WMBA 6623 Week 10: Risk Escalation Protocol
- WMBA 6623 Week 11: Quarterly Enterprise Risk Report
- WMBA 6627 Week 6: Workplace Conflict Case Analysis
- WMBA 6620 Week 6: Bottom-Up Project Cost Estimate
- WMBA 6615 Week 6: Culture Analysis Peer Replies
- WMBA 6608 Week 6: Capital Project Appraisal
WMBA 6623 Week 6 questions, answered
Where can I find a free WMBA 6623 Week 6 sample paper?
The quantitative risk analysis pricing eleven project risks is available on this page.
What is the total expected value?
About $412,550 across eleven priced risks.
Which risk is largest?
Escrow analysis errors, with an expected value of about $108,750.
What does the three-point estimate show?
A weighted mean near $470,000, above the most likely $435,000, because losses skew high.
What does expected value miss?
The full cost of rare, severe events, such as a late payment routing notice.