WMBA 6623 Week 3 Project Risk Register Example

Enterprise and Project Risk Management Walden University Free custom sample in 24 to 48h

This WMBA 6623 Week 3 project risk register example carries twelve threats and one opportunity for a composite bank's loan servicing consolidation across a wide table: ID, event, category, cause, effect, likelihood, impact, score, owner, response type and detail, residual score and review cadence. Owners are single job titles, never committees. Walden WMBA 6623 asks for the top risks to stand out, and four sit in the high band, led by the escrow analyst's knowledge at a score of 20 with a residual of 8 after training two analysts. MBA students see scoring rules stated first, ISO 31000 on treatment and residual risk, Cox on the limits of risk matrices and the PMBOK Guide on keeping the register current.

CourseWMBA 6623 Enterprise and Project Risk Management
WeekWeek 3
Paper typeRisk register
LengthAbout 950 words, 6 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramMaster of Business Administration (MBA)
UpdatedOctober 2026

Free sample paper for WMBA 6623 Week 3

1

Risk Register for the Loan Servicing Consolidation: Thirteen Entries With Named Owners, Scores, Responses and Residual Ratings, and the Four That Sit in the High Band

Student Name

Walden University

WMBA 6623: Enterprise and Project Risk Management

Instructor Name

Month Day, Year

What this page is doingThe title gives the count and the parts of each entry, then points to the four highest risks, which the register exists to make visible.
2

Risk Register for the Loan Servicing Consolidation: Thirteen Entries With Named Owners, Scores, Responses and Residual Ratings, and the Four That Sit in the High Band

How the Register Is Built

This register carries forward twelve threats and one opportunity from the risk identification for Lakeshore Community Bank's project to consolidate loan servicing from three offices into one Grand Rapids operations center. The bank is composite; its figures are illustrative.

Likelihood and impact are each rated from 1 to 5, using the scales defined for the project: likelihood 5 means more likely than not over the project's life, and impact 5 means a regulatory violation, borrower harm on more than 1,000 accounts or more than $250,000 of cost. The score is likelihood times impact. A score of 15 or more counts as high, 8 through 14 as medium and anything under 8 as low. Each owner is a single job title, not a committee, because a risk owned by a group is owned by no one. ISO 31000 describes risk treatment as selecting and implementing options to modify risk, followed by assessment of the residual risk (International Organization for Standardization, 2018), and the residual column records what the score should be once the response is in place.

What this page is doingThe scoring rules come first, so every number in the table can be read the same way.
3

The Register

Table 1

Risk Register, Loan Servicing Consolidation

IDRisk eventCategoryCauseEffectLIScoreOwnerResponse typeResponse detailResidualReview |
R02First consolidated escrow analysis runs without the Traverse City analyst's knowledgeStaffingProcess held in one analyst's spreadsheetsIncorrect escrow adjustments on thousands of accounts4520Mortgage Servicing ManagerMitigateDocument the spreadsheets and county exceptions; train a second analyst who runs the November 2026 cycle alongside her8Monthly |
R04Twenty new center roles still open at cutoverStaffingTight Grand Rapids labor marketPayment and call backlogs4416Human Resources DirectorMitigateStart recruiting six months early; offer relocation to Muskegon staff; use a temporary agency as backup8Monthly |
R10Escrow analyses for 9,000 accounts due in the cutover quarter are late or wrongRegulatoryAnalysis calendar overlaps cutoverRegulatory findings and refunds3515Escrow Operations SupervisorMitigateRun those analyses early, before data moves6Monthly |
R11Active loss mitigation files are lost or delayed in transferRegulatoryCases mid-review at closing officesMissed federal timelines and borrower harm3515Default Servicing ManagerMitigateKeep active cases with current staff until decided; transfer only closed files5Biweekly |
R01Local escrow and fee settings missed in consolidated configurationTechnicalThree offices configured differentlyIncorrect fees or payments3412Core Systems ManagerMitigateInventory all settings; run two parallel billing cycles before cutover4Monthly |
R05Key staff leave before their office closesStaffingLittle reason to stay through closureCoverage gaps4312Human Resources DirectorMitigateStay bonuses paid at closure for named roles6Monthly |
R06Payment routing notice to processor is lateVendor90-day contractual noticeMisrouted borrower payments2510Treasury Operations ManagerAvoidGive notice now, nine months ahead2Quarterly |
R09Servicing change notices to borrowers are late or incompleteRegulatoryFederal notice requirementsViolation and borrower confusion2510Compliance OfficerMitigateCompliance review of letters and mailing schedule4Monthly |
R07Core vendor's conversion team unavailable on planned datesVendorShared vendor resourcesTesting and cutover slip339Project ManagerTransferContract amendment naming a dedicated team, with a schedule penalty6Monthly |
R20Lease buildout finishes lateVendorLandlord's contractor scheduleDelayed move and added costs339Facilities ManagerTransferLease clause with rent abatement for late delivery6Monthly |
R13Paper loan documents lost or misfiled in moveTechnicalPaper files in three officesCannot support collection actions248Records ManagerMitigateImage all files before the move4Monthly |
R16Borrowers react negatively to losing the local officeChange adoptionValue placed on local serviceComplaints and lost relationships326Vice President, Retail BankingAcceptCommunication plan; local branches keep a servicing contact4Quarterly |
O1Collection practices standardized across officesOpportunityThree offices follow different practicesLower delinquency and simpler training339Collections ManagerExploitAdopt the best-performing office's practices as the standard9Quarterly |

L is likelihood and I is impact, each from 1 to 5; residual is the expected score after the response.

The High Band

Four risks score 15 or higher. The highest, R02, is the escrow analyst's knowledge, scored 20 because her retirement is nearly certain and an escrow error would affect thousands of accounts. Its response, a second analyst who runs a full cycle alongside her, reduces likelihood more than impact, which is why the residual score is 8 rather than lower. R04, hiring, and R10 and R11, both regulatory, follow. Three of the four involve people and compliance, the same pattern the bank saw in its 2019 conversion.

What this page is doingThe four highest risks are discussed in prose, because a reader should not have to search the table for them.
4

Notes on the Scores

The scores are ordinal judgments, not measurements. Cox (2008) showed that risk matrices can rank risks inconsistently, especially near band boundaries, so a score of 12 should not be read as twice as serious as a 6. The register will be used to decide where attention goes first, and the larger risks will be priced in dollars later in the term.

The register is reviewed at each project steering meeting. The PMBOK Guide recommends treating the register as a living document, updated as risks change and new ones emerge (Project Management Institute, 2017), and each row's review date sets how often its owner must report.

References

Cox, L. A., Jr. (2008). What's wrong with risk matrices? Risk Analysis, 28(2), 497-512. https://doi.org/10.1111/j.1539-6924.2008.01030.x

International Organization for Standardization. (2018). Risk management: Guidelines (ISO Standard No. 31000:2018).

Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.).

Reading the WMBA 6623 Week 3 instructions

The risk register assignment asks students to turn identified risks into a managed list. Instructors expect a wide table with columns for ID, risk event, category, cause, effect, likelihood, impact, score, owner, response type, response detail, residual score and review date, usually twelve to eighteen rows. Owners should be job titles held by one person, not committees. Scores should follow stated scales, and the highest risks should be visible without reading every row, often through banding. A short discussion of the top risks and the limits of the scores usually accompanies the table. Response details should be specific actions with dates, and residual scores should reflect what the action actually changes, likelihood, impact or both. Review dates show how often each owner must report.

How this WMBA 6623 Week 3 example is built

The paper explains the scales, bands and single-owner rule, citing ISO 31000 on treatment and residual risk. The register lists thirteen entries with all thirteen columns, from the escrow analyst and staffing to borrower reaction and an opportunity to standardize collections. A section discusses the four high-band risks and why the escrow response reduces likelihood more than impact. A section on the scores cites Cox on the ordinal nature of matrices and explains that later work will price the largest risks. A closing note cites the PMBOK Guide on keeping the register current and explains review dates. Margin comments flag the scoring rules and the high band. Scores are shown with their likelihood and impact so readers can check each product.

Where the marks sit in the WMBA 6623 Week 3 rubric

Graders reward a register in which every row is complete, with consistent scores, a single owner and a specific response. Distinguishing response types correctly, avoid, transfer, mitigate and accept, and including an opportunity, show understanding. Residual scores that reflect the response realistically carry weight. Making the top risks visible and discussing them demonstrates purpose. Acknowledging the limits of qualitative scores shows maturity. Registers in which every entry has a named owner and a trigger date are the ones graders treat as usable. Registers that explain why a response lowers likelihood rather than impact, or the reverse, show the strongest analysis. Including at least one opportunity shows the register is about uncertainty, not only threats.

WMBA 6623 Week 3 help from the desk

Carry forward your identified risks and score each on defined scales. Assign one person by job title to own each. Choose a response type and write a specific action, then estimate the score after the action. Set a review date. Sort or shade the table so the highest risks stand out. Students often lose marks by assigning owners to groups, by writing responses such as monitor closely or by leaving residual scores unchanged. Another frequent gap is ignoring opportunities. Add at least one. If you need a custom sample risk register for your project, send us your identified risks.

Get a WMBA 6623 Week 3 example written to your instructions

Pass along the Week 3 prompt, the rubric, and the column headings your template requires, and a filled register comes back on the organization of your choosing, owners and residual scores included. A first sample is free and turns around in 24-48 hours, laid out so the scale definitions sit where a grader looks for them.

More WMBA 6623 papers and MBA samples

WMBA 6623 Week 3 questions, answered

Where can I find a free WMBA 6623 Week 3 sample paper?

The project risk register for a bank's servicing consolidation appears in full on this page.

How many entries does it hold?

Twelve threats and one opportunity.

Which risk scores highest?

The escrow analyst's knowledge, at 20, falling to 8 after training two analysts.

Why are owners single job titles?

Because a risk owned by a group is owned by no one.

What limits do the scores have?

They are ordinal judgments, so a 12 is not twice as serious as a 6.