PUBH 6213 Week 5 Work Plan Example

Public Health Grant Writing Walden University Free custom sample in 24 to 48h

This PUBH 6213 Week 5 work plan example sets out the goal, three SMART objectives and every activity for a two-year school-based tele-audiology program, each with a responsible position and a span of months. Walden PUBH 6213 asks students to turn a program idea into promises a reviewer can check, and this brief gives each objective a baseline from last year's referral logs and sets the completed-evaluation target below the rate reached in an Alaska trial, because a new program spends its first semester building routines. The activity table shows three months of setup before any child is seen and a care coordinator who owns every referral. Hiring and school board risks are named with responses. MPH students can see how the work plan and logic model share wording so reviewers never translate between them.

CoursePUBH 6213 Public Health Grant Writing
WeekWeek 5
Paper typeGrant work plan
LengthAbout 870 words, 6 pages
FormatAPA 7 student paper
SchoolWalden University
ProgramMaster of Public Health (MPH)
UpdatedOctober 2026

Free sample paper for PUBH 6213 Week 5

1

Every Promise With an Owner and a Month: A Two-Year Work Plan With Three SMART Objectives for a Composite County's School-Based Tele-Audiology Follow-Up Program

Student Name

Walden University

PUBH 6213: Public Health Grant Writing

Instructor Name

Month Day, Year

What this page is doingThe title names what a reviewer checks in a work plan, an owner and a month for each promise, so the table is read for exactly that.
2

Every Promise With an Owner and a Month: A Two-Year Work Plan With Three SMART Objectives for a Composite County's School-Based Tele-Audiology Follow-Up Program

Goal

Children in Tamarack County who fail a school hearing rescreen will receive a diagnostic hearing evaluation quickly, close to where they learn, whatever their family's distance from a specialist or insurance status.

What this page is doingA goal stated in plain words, without numbers, leaves the objectives to carry the measurable promises.
3

Objectives

The three objectives below follow the SMART pattern: each is specific, measurable, achievable within the grant, relevant to the announcement's purpose and bound to a date. Each also has a baseline drawn from last school year's nurse referral logs, in which 54 of 168 referred children, about 32%, had any documented evaluation before June.

Objective 1, timely access. By month 12, no fewer than 85% of children who fail a school hearing rescreen in the four participating districts will be offered a tele-audiology appointment at their school within 30 days of referral. Baseline: no school-based option existed, so the baseline is 0%.

Objective 2, completed evaluation. Within the first 12 months, 65% or more of referred children will complete a diagnostic hearing evaluation within 90 days of referral, rising to 75% by the end of month 24. Baseline: about 32% completed an evaluation at any point in the school year.

Objective 3, results reach the family and school. By the end of month 12, 100% of children diagnosed with a hearing loss will have results explained to a parent or guardian and, with written permission, shared with the school's student support team within 14 days of diagnosis.

The targets in Objective 2 are set below the 68.5% follow-up rate achieved through school-based telemedicine in rural Alaska (Emmett et al., 2022), because Tamarack's program is new and its first semester will be spent building the referral routine. Setting a target the program can plausibly reach protects credibility with the funder and with partners.

Activities

Table 1

Work Plan by Objective, Activity, Responsible Position and Months

ObjectiveActivityResponsible positionMonths |
AllHire and train care coordinatorProgram manager1 to 3 |
AllSign data sharing agreements with four districtsProgram manager; district superintendents1 to 3 |
1Purchase and calibrate four tablet audiometer kits and video otoscopesCare coordinator; contracted audiologist2 to 3 |
1Train school nurses on rescreen protocol and referral formContracted audiologist3 |
1Schedule tele-audiology clinic days at each school, twice monthlyCare coordinator4 to 24 |
2Conduct school-based evaluations with remote audiologist reviewCare coordinator; contracted audiologist4 to 24 |
2Call families before each clinic day; arrange consent and insurance informationCare coordinator4 to 24 |
2Refer children needing medical or further audiology care and track completionCare coordinator4 to 24 |
3Explain results to the family, by call or visit, inside 14 daysContracted audiologist; care coordinator4 to 24 |
3Share results with school support team when families permitCare coordinator; school nurses4 to 24 |
AllMaintain referral log and submit quarterly data to evaluatorCare coordinator4 to 24 |
AllQuarterly partner meeting to review data and adjust scheduleProgram manager6, 9, 12, 15, 18, 21, 24 |
AllAnnual report to funderProgram manager; evaluator12, 24 |

Note. Months count from the award start date.

How the Plan Fits Together

The first three months build the system before any child is seen. Hiring, data agreements, equipment and training must all be finished by month 3, which is why the first clinic days start in month 4, not month 1. A reviewer will look for that sequence because programs that schedule services in month 1 often spend their first quarter explaining delays.

The care coordinator appears in most rows, which is intentional. The single most important change from current practice is that one person owns each referral from the day it is made until the family has results. In the current system, the referral letter goes home in a backpack and no one is responsible for what happens next. A review of school hearing screening programs worldwide described follow-up losses in nearly every setting and found that few programs gave anyone responsibility once a referral was made (Yong et al., 2020). The work plan answers that finding by putting a name on every step.

Risks to the Timeline

Two risks could delay the plan. Hiring in a rural county can take longer than three months, so the program manager will advertise in the regional nursing and health technician networks before award and will cover clinic days personally if needed. The second risk is district approval of data sharing, which depends on four school boards meeting on their own calendars. Letters of commitment from all four superintendents are already being requested, and the agreements will follow the same template to speed review.

Alignment With the Logic Model

Each activity in the table links to an output (clinic days held, children evaluated, results shared) and each output to an objective. The one-page logic model attached to the application lists the same activities in the same words, as recommended in the guidance the department follows for program planning (W. K. Kellogg Foundation, 2004), so that reviewers can move between documents without translating.

What this page is doingMatching words across documents is a small courtesy that saves reviewers time and prevents mismatched scoring.
4

References

Emmett, S. D., Platt, A., Turner, E. L., Gallo, J. J., Labrique, A. B., Inglis, S. M., Jenson, C. D., Parnell, H. E., Wang, N.-Y., Hicks, K. L., Egger, J. R., Halpin, P. F., Yong, M., Ballreich, J., & Robler, S. K. (2022). Mobile health school screening and telemedicine referral to improve access to specialty care in rural Alaska: A cluster-randomised controlled trial. The Lancet Global Health, 10(7), e1023-e1033. https://doi.org/10.1016/S2214-109X(22)00184-X

W. K. Kellogg Foundation. (2004). Logic model development guide. https://wkkf.issuelab.org/resource/logic-model-development-guide.html

Yong, M., Panth, N., McMahon, C. M., Thorne, P. R., & Emmett, S. D. (2020). How the world's children hear: A narrative review of school hearing screening programs globally. OTO Open, 4(2). https://doi.org/10.1177/2473974X20923580

Reading the PUBH 6213 Week 5 instructions

Work plan assignments ask students to lay out what their program will do, by whom and when. Prompts typically require a goal, two to four SMART objectives with baselines, activities for each objective, responsible persons or positions, timelines and sometimes outputs or measures. A table is expected, usually with a short narrative explaining the sequence. Many instructors ask that objectives be realistic and tied to evidence, and that the work plan align with the budget and evaluation. Expect two to four pages. Strong work plans show setup time, assign ownership clearly and anticipate risks to the timeline, while weak ones list activities without owners or schedule services before the staff and equipment needed for them exist.

How this PUBH 6213 Week 5 example is built

The brief states a plain goal, then three numbered objectives, every one carrying a target, a date and a baseline from last year's logs. A paragraph explains why one target sits below the trial benchmark. The activity table follows, organized by objective, with a responsible position and months for every row, including setup tasks, clinic operations, family contact, results sharing, data reporting and partner meetings. A section explains the sequence and why the care coordinator appears in most rows, connecting that choice to evidence on loss to follow-up. A section names two timeline risks with responses, and a final paragraph links the plan's wording to the logic model.

Where the marks sit in the PUBH 6213 Week 5 rubric

Graders evaluate whether objectives are truly SMART, with measurable targets, deadlines and baselines, and whether they connect to the need statement. The activity table is judged on completeness and logic: every objective needs activities, every activity needs an owner and timeline, and setup must come before services. Realism carries weight, so targets should be justified by evidence or local data. Credit also goes to anticipating risks and to alignment with the logic model, budget and evaluation. A clear table and a short narrative that explains rather than repeats it are expected. APA citations support targets drawn from published studies. Plans that include partner meetings to review data and adjust schedules show the reviewer a program that expects to learn as it runs. A missing owner on even one row tends to cost more than a missing month, since ownership is what reviewers test first.

Common PUBH 6213 Week 5 mistakes, and how to avoid them

Common problems include objectives that describe activities rather than results, targets with no baseline and activities that begin on the first day of the grant. Write objectives as changes in the people you serve, with a number and a date. Give every row in your table one responsible position. Leave time at the start for hiring, agreements and equipment. Check that each activity has a cost in the budget and a measure in the evaluation. Explain how you chose your targets. Name what could delay the plan and how you will respond. We can help shape a work plan from your own program idea and your instructor's template.

Get a PUBH 6213 Week 5 example written to your instructions

Paste the work plan prompt, its rubric and your objectives in draft, and a table assigning each activity to a position and a span of months arrives in 24-48h; the first comes free. The coordinator, hygienist and health worker are positions in a fictional program, so the roles in your plan reflect the staffing your proposal can actually support.

More PUBH 6213 papers and MPH samples

PUBH 6213 Week 5 questions, answered

Where can I find a free PUBH 6213 Week 5 sample paper?

The full Week 5 work plan is printed above, with three SMART objectives for a school-based tele-audiology program.

What makes an objective SMART?

It names a specific change, a number, a realistic level, a link to the need and a date, ideally against a baseline.

Why do clinic days start in month 4?

Hiring, data sharing agreements, equipment and training must be finished first, and starting services early often leads to delays.

Why is the evaluation target below the trial's result?

A new program needs time to build routines, so a realistic target protects credibility with the funder and partners.

Why does one position appear in most rows of the plan?

The program's key change is that one person owns each referral from the failed rescreen until results reach the family.