Free sample paper for MGMT 8009M Week 7
Funded After the Sponsor Left: An Escalation Case Following a Distributor's Four-Year System Replacement as Commitment Moved From One Executive's Judgment Into Departments, Contracts and a Review Template
Student Name
Walden University
MGMT 8009M: Organizational Decision Making and Judgment
Instructor Name
Month Day, Year
Funded After the Sponsor Left: An Escalation Case Following a Distributor's Four-Year System Replacement as Commitment Moved From One Executive's Judgment Into Departments, Contracts and a Review Template
Four Budgets in a Row
Wexley Supply, a composite wholesale distributor of electrical and plumbing products with 22 branches, approved the replacement of its order management and warehouse systems in early 2021. The project was scheduled for 18 months and budgeted at $6.2 million. Four years later it was still running.
[after]
The wording of the review question is taken from the agenda of each finance committee meeting. It changed once, between years 1 and 2, and then did not change again.
Table 1
Annual Funding Reviews of the System Replacement Project
| Review | Approved budget to date | Spend to date | Promised go-live | Question the review asked | |
|---|---|---|---|---|
| Year 1, March 2022 | $8.1 million | $5.9 million | December 2022 | Is the project on track to deliver the approved scope? | |
| Year 2, March 2023 | $10.4 million | $8.8 million | September 2023 | What is required to complete the approved scope? | |
| Year 3, March 2024 | $13.0 million | $11.6 million | June 2024 | What is the cost to complete? | |
| Year 4, March 2025 | $15.3 million | $14.1 million | March 2025, partial | What is the cost to complete? | |
The Model Used to Read the Pattern
Staw and Ross (1989) organized the causes of escalation into four groups: project determinants, such as the expected payoff and the size of the remaining cost; psychological determinants, such as self-justification and the reluctance to admit a loss; social determinants, such as the need to appear consistent before others; and structural determinants, such as the political support and institutional arrangements that grow around a project. They argued that these determinants operate at different times, with project and psychological factors often dominant early and structural ones later. The case uses that model year by year rather than assigning one cause to the whole period.
Year One Belongs to the Sponsor
The project's sponsor was the chief operating officer, who had presented it to the board in 2021 as the centerpiece of a modernization plan. At the first review, the project was already $1.9 million over its original budget. The sponsor argued for continuing, citing the vendor's progress and the cost of reverting to the old system. In the experiment reported by Staw (1976), participants who had themselves chosen an investment that then performed poorly put more new money into it than participants who inherited the same choice from someone else. The first continuation fits that finding well: the sponsor was publicly tied to the project, the overrun was modest, and admitting failure after one year would have been costly to her standing. Social determinants also appear. The board minutes record the sponsor describing the project as "the decision we made together," which tied the board's own consistency to the choice.
The Second Year: Mixed Determinants
By the second review the overrun had grown and the question had shifted from whether the project was on track to what was required to finish. Project determinants still mattered. The vendor reported that about 70 percent of configuration was complete, and the remaining cost looked smaller than the cost already spent. But the change in the review question is the first structural sign. A question about requirements to complete assumes completion.
The Department That Needed the Project
In mid-2023 Wexley created a business systems department of twenty staff to run the implementation, train branches and maintain interfaces. The department's charter stated its purpose as delivering the new platform. From that point, a decision to stop the project would also have been a decision to dissolve a department, reassign its staff and write off its training investment. Ross and Staw (1993), in their study of the Shoreham nuclear power plant, described how the arrangements built around a long project came to support its continuation independently of any individual's judgment. The org chart shows the same development at Wexley. Structural determinants are visible in documents, not inferred.
The vendor contract was also amended in 2023. The amendment extended the schedule and added exit fees that rose with each phase completed, so stopping in 2024 would have cost about $1.1 million in fees alone.
Funding Without the Sponsor
In January 2024 the sponsor moved to lead a newly acquired division. Her successor had no part in the original decision. If escalation at Wexley had been driven by the sponsor's need to justify her choice, her departure should have opened the way to a fresh look. It did not. The March 2024 review approved another $2.6 million on the same question, cost to complete, and the March 2025 review did the same. The successor's memo to the finance committee in 2024 discussed only how to finish faster.
The Question the Review Asked
The case argues that the review question itself made continuation the default answer. A committee asked what it will cost to finish compares remaining cost with remaining benefit and will often find finishing worthwhile, however much has been spent, because the spent amount is sunk. That comparison is sound on its own terms, yet it never asks whether the project, knowing what is now known, should be started today, and it never compares the project with alternatives such as a phased replacement or a different vendor. The template excluded the question that would have exposed the escalation.
Recommendations
Three changes address the structural determinants the case found. Each annual review should ask whether the organization would approve the project today, at the remaining cost, against named alternatives. A reviewer with no role in the project, such as the internal audit director, should prepare the alternatives. And project departments should be chartered for a fixed term with a stated review, so that their continuation is a separate decision. Advising leaders to admit mistakes would address only the first year.
Limits
Wexley is a composite case. Its record is constructed to show a pattern common in system replacements, and a real record would likely contain more ambiguity about when the determinants shifted.
References
Ross, J., & Staw, B. M. (1993). Organizational escalation and exit: Lessons from the Shoreham nuclear power plant. Academy of Management Journal, 36(4), 701-732. https://doi.org/10.2307/256756
Staw, B. M. (1976). Knee-deep in the big muddy: A study of escalating commitment to a chosen course of action. Organizational Behavior and Human Performance, 16(1), 27-44. https://doi.org/10.1016/0030-5073(76)90005-2
Staw, B. M., & Ross, J. (1989). Understanding behavior in escalation situations. Science, 246(4927), 216-220. https://doi.org/10.1126/science.246.4927.216
What the MGMT 8009M Week 7 instructions ask for
Week 7 asks you to analyze a case of escalating commitment. Expect to present the project's history year by year, ideally from funding documents, and then explain each continuation using a model of escalation, usually Staw and Ross's project, psychological, social and structural determinants. Instructors want the explanation to fit each period rather than one cause for the whole story. Look for evidence that separates individual from organizational commitment, such as a change of sponsor. Examine the question decision makers were asked at each review, since its wording often shapes the answer. Close with changes to the review process. Plan on six or seven pages, and put the funding history in one exhibit. Note any change in sponsor, contract or organization chart, because those moments often separate the explanations.
How this MGMT 8009M Week 7 example is built
The sample's exhibit lists four annual reviews with budget, spend, promised go-live and the review question, quoted from finance committee agendas. A section explains Staw and Ross's four determinant groups and their timing. Year one is assigned to the sponsor, with Staw's research on personal responsibility and a quoted line tying the board's consistency to the choice. Year two shows mixed determinants and the first structural sign, a reworded question. A section on the new department and the amended contract shows structure in documents. The sponsor's move to another division is treated as the decisive fact. A section on the review question argues that it excluded alternatives, and three recommendations follow.
MGMT 8009M Week 7 rubric: what earns full marks
Graders look mainly for an explanation that changes as the case moves through time. A paper attributing four years of funding to one executive's ego fits the first year and then stops explaining. Credit concentrates in a year-by-year assignment of determinants, each backed by a document. Finding a fact that separates individual from organizational commitment, such as funding that continues after the sponsor leaves, is rewarded strongly. The review question earns credit when it is quoted or reconstructed. Recommendations should address structure; advising leaders to admit mistakes addresses only the early period. A clear exhibit and accurate APA references fill out the MGMT 8009M Week 7 score. A short note on what the case cannot show, given the documents available, is also valued.
MGMT 8009M Week 7 help: mistakes that cost marks
A common weakness is a single cause for the whole history, usually the sponsor's pride. Lay out each funding decision in sequence first and ask what changed between them: people, contracts, departments, the wording of the review. Look for the moment when the project acquired its own structure, since that is often when commitment stopped depending on any individual. Quote the question each review asked if you can find it. Give the individual explanation its due for the early period. Recommend changes that alter what the next review asks. A tutor can help you reconstruct a project's funding history, and the distributor case above shows one approach in full. Keep the exhibit to one page so the pattern is visible at a glance.
Get a MGMT 8009M Week 7 example written to your instructions
Send the Week 7 prompt, the rubric and the project or case you are examining, and an escalation case with its year-by-year exhibit returns within 24-48h at no charge the first time. Mention how many funding decisions your case covers and whether the sponsor stayed in role throughout.
More MGMT 8009M papers and PhD in Management samples
- MGMT 8009M Week 1: Process Critique
- MGMT 8009M Week 2: Bounded Rationality Memo
- MGMT 8009M Week 3: Framing Analysis
- MGMT 8009M Week 4: Heuristics Review
- MGMT 8009M Week 5: Decision Reconstruction
- MGMT 8009M Week 6: Group Process Case
- MGMT 8009M Week 8: Information Flow Memo
- MGMT 8009M Week 9: Incentive Analysis
- MGMT 8009M Week 10: Debiasing Design
- MGMT 8009M Week 11: Decision Audit
- MGMT 8003M Week 7: Draft Problem Statement
MGMT 8009M Week 7 questions, answered
Where can I find a free MGMT 8009M Week 7 sample paper?
Above is the distributor system replacement escalation case, the complete Week 7 sample.
What escalation model does the MGMT 8009M Week 7 case use?
Staw and Ross's model, which groups causes into project, psychological, social and structural determinants that shift over time.
Why does the sponsor's departure matter in the case?
Funding continued without her, which shows commitment had moved from one person's self-justification into the organization's structure.
What question did the funding reviews ask?
After the first year, what it would cost to complete, rather than whether the project should be started today.
What does the Week 7 case recommend?
Asking each review whether to approve the project today against named alternatives, prepared by an independent reviewer.