| Course | WMBA 6070 Managerial Finance |
|---|---|
| Week | Week 5 |
| Paper type | Capital project memo |
| Length | About 770 words, 4 pages |
| Format | Memo, APA 7 citations |
| School | Walden University |
| Program | Master of Business Administration (MBA) |
| Updated | October 2026 |
Free sample paper for WMBA 6070 Week 5
Memorandum
To: Owners, Brightwater Crane and Rigging
From: Finance Manager
Date: October 19, 2026
Re: Investment decision on the proposed 250-ton all-terrain crane
Decision
Brightwater should buy the 250-ton all-terrain crane. Discounted at the firm's 10.5 percent cost of capital from the Week 4 memo, its cash flows over twelve years are worth about $478,000 more than they cost. Two supporting measures agree: the crane returns roughly 14.4 percent a year on the money committed, and the investment is recovered in about six years. The project's main risk is utilization. If the crane works fewer than about 1,250 billable hours a year, instead of the 1,450 assumed, it no longer earns its cost of capital.
The Cash Flows
The crane costs $2.4 million, paid under the four-payment schedule chosen in Week 1, plus about $60,000 of working capital for parts and receivables. The analysis treats the full price as spent at delivery, since the payment schedule is a financing choice and should not be mixed into the investment decision (Brealey et al., 2023).
Table 1
Assumptions Behind the Cash Flows
| Item | Assumption | Basis | |
|---|---|---|
| Billable hours per year | 1,450 | The firm's large cranes averaged 1,380 to 1,520 hours over three years | |
| Operated rental rate | $600 per hour | Current rate card for 200- to 300-ton cranes | |
| Fixed annual costs | $180,000 | Insurance, annual inspection, permits and storage | |
| Variable costs | $165 per billable hour | Operator and oiler wages, fuel, maintenance | |
| Depreciation | Five-year MACRS | Tax class for construction equipment | |
| Life and salvage | 12 years; $700,000 before tax | Resale values for 12-year-old cranes of this class | |
| Tax rate | 21% | Owners' pass-through rate used in Week 4 | |
Figures are composite estimates for a composite firm.
Each year the crane earns about $870,000 in rental revenue and costs about $419,000 to run. After tax and the tax savings from depreciation, it produces about $457,000 of cash in year one, falling to about $356,000 a year once depreciation ends after year six, with about $613,000 more in year twelve from the after-tax salvage value and the return of working capital.
Results
Table 2
Measures at the Base Case
| Measure | Result | |
|---|---|
| Net present value at 10.5% | About $478,000 | |
| Return on money committed (IRR) | About 14.4% | |
| Payback period | About 6 years | |
| Profitability index | About 1.19 | |
Composite figures.
The net present value is the measure that decides the case, because it shows the dollar value the project adds at the firm's own cost of capital. The 14.4 percent return confirms a margin of about four points over the hurdle. Payback is long, as it usually is for heavy equipment, and it says more about how long the firm's cash is committed than about the project's value. The profitability index of about 1.19, the present value of the inflows divided by the initial outlay (Ross et al., 2022), means each dollar invested returns about $1.19 in present value.
Sensitivity
Table 3
Net Present Value When One Assumption Changes
| Change | Net present value | |
|---|---|
| Billable hours fall to 1,300 | About $135,000 | |
| Billable hours fall to 1,160 (20% below base) | About -$185,000 | |
| Billable hours rise to 1,600 | About $821,000 | |
| Rental rate falls to $540 | About $21,000 | |
| Discount rate rises to 13% | About $152,000 | |
| Salvage value falls to $400,000 | About $407,000 | |
Each row changes one assumption and holds the others at the base case; composite figures.
Utilization and the rental rate matter most. The project breaks even at about 1,250 billable hours, about 14 percent below the base case, or at a rate near $540, about 10 percent below the current card. The discount rate matters less: even at 13 percent, the rate proposed in Week 4 for the riskier wind venture, the crane adds value. Salvage value barely matters, because it arrives twelve years from now.
Why the Risk Is Acceptable
Utilization below 1,250 hours would require a sharp downturn in commercial construction in the firm's region. In its worst recent year, Brightwater's large cranes still averaged about 1,300 hours. In the survey by Graham and Harvey (2001), most finance chiefs leaned on discounted measures for big decisions and often looked at payback too; here every one of those measures favors the crane. The memo nonetheless recommends one protection: before delivery, the sales team should line up commitments for at least 600 of the first year's hours from the firm's two largest contractor customers.
Commitment
Fund the purchase at $2.4 million under the four-payment schedule, with delivery in the spring, and review the crane's billable hours at the end of its first full season.
References
Brealey, R. A., Myers, S. C., & Allen, F. (2023). Principles of corporate finance (14th ed.). McGraw Hill.
Graham, J. R., & Harvey, C. R. (2001). The theory and practice of corporate finance: Evidence from the field. Journal of Financial Economics, 60(2-3), 187-243. https://doi.org/10.1016/S0304-405X(01)00044-7
Ross, S. A., Westerfield, R. W., Jaffe, J., & Jordan, B. D. (2022). Corporate finance (13th ed.). McGraw Hill.
What the WMBA 6070 Week 5 instructions ask for
Capital budgeting cases in managerial finance hand students a project with a cost, a stream of cash flows and a stated life, and ask for a verdict. Prompts usually require the discounted result, one or two supporting measures, a short sensitivity analysis and a paragraph committing the firm to fund the project or not. Instructors expect cash flows built on stated assumptions, financing kept separate from the investment decision, taxes and depreciation handled correctly and a sensitivity that identifies which assumptions could reverse the verdict. A protection that addresses the most dangerous assumption, such as a customer commitment or a staged purchase, strengthens a positive recommendation considerably.
Inside the WMBA 6070 Week 5 example
The memo opens with the decision, the key measures and the variable that could reverse it. A section explains that the payment schedule is a financing choice kept out of the analysis, citing Brealey and colleagues. A table lists assumptions with their basis. A paragraph describes revenue, costs and the after-tax cash flows, including the salvage value and the return of working capital. A results table lists the four measures, and the text says why the discounted dollar value decides, with Ross and colleagues on the profitability index. A one-variable-at-a-time table follows, and the text finds the hours and hourly rate where value disappears. A section judges the risk acceptable, cites Graham and Harvey on measures firms use and adds a protection. Margin comments flag the cash flows, the sensitivity and the protection.
WMBA 6070 Week 5 rubric: what earns full marks
Graders reward cash flows built from explicit assumptions, with depreciation, taxes, salvage and working capital handled correctly. The discounted result should use the firm's cost of capital, and supporting measures should be interpreted rather than listed. The sensitivity run carries significant weight: changing one assumption at a time and reporting breakeven points shows which risks matter. A clear commitment, with a reason the risk is acceptable or not, completes the case. Adding a practical protection against the key risk often distinguishes the strongest memos. Instructors also check that financing costs are not double-counted in the cash flows. Graders also confirm that the after-tax salvage and working capital appear in year twelve.
Common WMBA 6070 Week 5 mistakes, and how to avoid them
Write down every assumption, with its basis, before building the cash flows. Leave loan payments out of the project's cash flows, since the hurdle rate already charges for money. Include depreciation only for its tax effect, and remember salvage value and working capital at the end. Compute net present value at the firm's cost of capital, then the internal rate of return and payback. Change one assumption at a time and find where the result turns negative. Students often lose marks by mixing loan payments into project cash flows, by forgetting taxes on salvage or by listing measures without interpreting them. Commit to a decision. Add a protection if the result depends on one variable. If you would like a custom sample capital project memo, send us your project's figures.
Get a WMBA 6070 Week 5 example written to your instructions
Attach the Week 5 case file, the rubric, and the rate your section wants used if one was given, and a finished capital budget memo is returned inside 24 to 48 hours, the first at no cost. Where a spreadsheet has to accompany the memo, the sample ships with one whose cells recompute when an assumption is changed.
More WMBA 6070 papers and MBA samples
- WMBA 6070 Week 1: Payment Schedule Comparison
- WMBA 6070 Week 2: Risk and Return Post
- WMBA 6070 Week 3: Private Note Valuation Brief
- WMBA 6070 Week 4: Hurdle Rate Memo
- WMBA 6070 Week 6: Debt Versus Equity Financing
- WMBA 6070 Week 7: Capital Budget Allocation
- WMBA 6070 Week 8: Final Plan and Reflection
- WMBA 6201 Week 5: Measure Collection Replies
- WMBA 6060 Week 5: Product and Pricing Analysis
- WMBA 6401 Week 5: Engagement Survey Readout
- WMBA 6050 Week 5: Flexible Budget Variance Report
WMBA 6070 Week 5 questions, answered
Where can I find a free WMBA 6070 Week 5 sample paper?
The capital project memo for a 250-ton crane, with its sensitivity run, is reproduced in full below.
What is the net present value?
About $478,000 at a 10.5 percent cost of capital.
What return does the crane earn on its cost?
About 14.4 percent a year.
Which assumption matters most?
Billable hours; the project breaks even near 1,250 hours a year instead of the assumed 1,450.
What protection does the memo add?
Commitments from the two largest customers for at least 600 hours before delivery.